Permit: T20CM02165
Permit Details
Apply Date:
04/09/2020
Applicant:
HELEN ORMSBY
Description:
SFR DRHRT2960 T19-M0071
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM02165
Permit Status: Final
Permit Description: SFR DRHRT2960 T19-M0071
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/15/2020 | ACTIVE |
Completed Inspections
Permit Status: Final
Permit Number: T20CM02165
Permit Description: SFR DRHRT2960 T19-M0071
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/14/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | RVI |
04/14/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | RVI |
04/14/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | RVI |
04/22/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
04/22/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | RVI The TEP clearance code is ECO. |
04/22/2020 | ELECTRIC - UFER | ESTEVENS | Approved | RVI |
04/22/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | RVI |
04/22/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | RVI |
04/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | RVI |
06/22/2020 | ROOF NAILING | TVALENCIA | Approved | approved |
06/22/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | approved |
07/16/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
07/16/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
07/16/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
07/16/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
07/16/2020 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
07/16/2020 | FRAMING | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
07/22/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | Approved |
09/23/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
09/23/2020 | PLUMBING - FINAL | DQUINN | Approved | Ap |
09/23/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
09/23/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
09/28/2020 | BUILDING - FINAL | KEN | Approved | CERT FILED |