Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
02/19/2020
Applicant:
Description:
SFR LENN400119 T19-M0124

Permit Reviews

Permit Number - T20CM01130
Permit Status: Expired
Permit Description: SFR LENN400119 T19-M0124
Start Date Submittal Complete Date Status  
02/19/2020 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 02/20/2020 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T20CM01130
Permit Status: Expired
Permit Description: SFR LENN400119 T19-M0124
Total Outstanding Activity Conditions - 1
Date Name
02/19/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Conditions

Permit Number - T20CM01130
Permit Status: Expired
Permit Description: SFR LENN400119 T19-M0124
Date Description Comments
09/04/2020 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T20CM01130
Permit Description: SFR LENN400119 T19-M0124
Total Completed Inspections - 22
Date Description Inspector Results Comments
03/10/2020 COT - RSPL - Yard Water Line Passed {Activity date: 03/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
03/10/2020 COT - RSPL - Sewer Passed {Activity date: 03/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
03/10/2020 COT - RSPL - Rough Soil Passed {Activity date: 03/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
03/17/2020 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by SFLORES2 - }
03/17/2020 COT - RSBU - Preslab Passed {Activity date: 03/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by SFLORES2 - }
03/17/2020 COT - RSEL - Electrical Underground Passed {Activity date: 03/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by SFLORES2 - }
04/13/2020 COT - RSBU - Roof Nailing Passed {Activity date: 04/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
04/13/2020 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 04/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - LCBU - Framing Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - LCPL - Plumbing Intermediate Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - BULD - SWG Clearance Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE}
05/13/2020 RSME - Mechanical Progress Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - RSPL - Gas Pressure Test Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Clear Southwest Gas.}
05/13/2020 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/15/2020 PDSD Building Division - TEP PM Clearance Passed {Activity date: 05/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE ECO}
05/15/2020 COT - RSEL - Construction Power Passed {Activity date: 05/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved Clear TEP ECO}
08/05/2020 COT - RSME - Mechanical Final Passed {Activity date: 08/05/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
08/05/2020 COT - RSEL - Outdoor Lighting Passed {Activity date: 08/05/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
08/05/2020 COT - RSPL - Plumbing Final Passed {Activity date: 08/05/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
08/05/2020 COT - RSEL - Electrical Final Passed {Activity date: 08/05/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
09/04/2020 RSBU - Building Final Passed {Activity date: 09/04/2020; Status: Approved; Inspector: KEN; Comment: Entered by KKARSEN1 - CERT FILED} ; {Activity date: 08/05/2020; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - INSPECTOR APPROVED BUILDING FINAL. PENDING SPECIAL INSPECTION.}

Documents

File Name Document Type  
SIC.PDF DOCUMENTS VIEW