Permit: T20CM00733
Permit Details
Apply Date:
01/31/2020
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHOH35A19 T19-M0141
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM00733
Permit Status: Final
Permit Description: SFR DRHOH35A19 T19-M0141
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/03/2020 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 02/03/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00733
Permit Status: Final
Permit Description: SFR DRHOH35A19 T19-M0141
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/31/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM00733
Permit Description: SFR DRHOH35A19 T19-M0141
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/21/2020 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | RVI |
02/21/2020 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | RVI |
02/21/2020 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | RVI |
02/28/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
02/28/2020 | ELECTRIC - UFER | ESTEVENS | Approved | |
02/28/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
02/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
03/18/2020 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
03/18/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric ECO |
03/18/2020 | ROOF NAILING | TVALENCIA | Approved | |
03/18/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
04/14/2020 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
04/14/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
04/14/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas |
04/14/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
04/14/2020 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
04/29/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | RVI |
07/10/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | All three are approved. |
07/10/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | All three are approved. |
07/10/2020 | PLUMBING - FINAL | ESTEVENS | Approved | All three are approved. |
07/10/2020 | FRAMING | ESTEVENS | Approved | SEE 1090 |
07/13/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Both are approved. |
07/13/2020 | BUILDING - FINAL | ESTEVENS | Approved | Both are approved. |