Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM00715
Permit Details
Apply Date:
01/30/2020
Applicant:
Description:
TEMP CONSTRUCTION TRAILER
Permit Reviews
Permit Number - T20CM00715
Permit Status: Expired
Permit Description: TEMP CONSTRUCTION TRAILER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2020 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/11/2020 | COMPLETED |
02/11/2020 | RESUBMITTAL | 02/12/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00715
Permit Status: Expired
Permit Description: TEMP CONSTRUCTION TRAILER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/30/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM00715
Permite Description: TEMP CONSTRUCTION TRAILER
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | PDSD Site/Engineering Division - NPPO | N/A | Canceled | Inspection Canceled |
11/04/2022 | TRSP - ROW - Final/Close-Out | N/A | Canceled | Inspection Canceled |
11/04/2022 | ENGR Engineering Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM00715
Permit Description: TEMP CONSTRUCTION TRAILER
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/20/2020 | COT - LCEL - Electrical Underground | Passed | {Activity date: 02/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI CLEAR TMPC} |
|
02/20/2020 | BULD - Electrical Clearance | Passed | {Activity date: 02/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by DMERANZ1 - CODE TMPP} | |
02/20/2020 | COT - LCEL - Service Upgrade | Passed | {Activity date: 02/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI CLEAR TMPC} |
|
02/20/2020 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 02/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI CLEAR TMPC} |
|
04/09/2020 | COT - LCBU - Building Final | Passed | {Activity date: 04/09/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
04/09/2020 | COT - LCEL - Electrical Final | Passed | {Activity date: 04/09/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } |