Permit: T20CM00704
Permit Details
Apply Date:
01/30/2020
Applicant:
N/A
Description:
E - NEW OFFICE BUILDING
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T20CM00704
Permit Status: C of o
Permit Description: E - NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2020 | PLANS OK TO SUBMIT - COMM | 03/03/2020 | COMPLETED |
| 03/03/2020 | 3RD PARTY REVIEW - COMMERCIAL | 04/17/2020 | COMPLETED |
| 04/17/2020 | POST 3RD PARTY REVIEW | 04/30/2020 | COMPLETED |
| 09/23/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 09/23/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00704
Permit Status: C of o
Permit Description: E - NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/30/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM00704
Permit Description: E - NEW OFFICE BUILDING
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2020 | STEM WALL/RETAINING WALL | JBURGE | Approved | Center stem walls; Southwest; West; and Northwest stem walls. Ok to place concrete. |
| 05/22/2020 | ELECTRIC - UNDERGROUND | JBURGE | Approved | |
| 05/22/2020 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | |
| 05/22/2020 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | |
| 05/28/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | |
| 05/28/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 07/28/2020 | ROOF NAILING | WGALLAGHER | Approved | Approved |
| 08/07/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | Approved |
| 08/17/2020 | FRAMING | WGALLAGHER | Approved | Approved |
| 08/19/2020 | PLUMBING - ROOF DRAINS | WGALLAGHER | Approved | Approved |
| 08/28/2020 | PLUMBING - ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 08/28/2020 | ELECTRIC - INTERMEDIATE | TTREMBULAK | Approved | Approved |
| 08/28/2020 | PLUMBING - INTERMEDIATE | TTREMBULAK | Approved | Approved |
| 09/01/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | Approved |
| 09/18/2020 | PLUMBING - MD GAS/PRECONST MTG | DQUINN | Approved | na |
| 09/18/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 09/18/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | Ap |
| 09/18/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 10/02/2020 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE INCR |
| 10/02/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | Approved ok for clearance INCR |
| 10/12/2020 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
| 10/12/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ok to drop tiles. |
| 11/03/2020 | FIRE - FINAL | wmotto1 | Approved | 1. Need knox locking cap on sprinkler connection. 2. Need fire extinguishers. 3. Need to lable the riser room and fire alarm rooms. 4. Ok for temp c of o per tucson fire. |
| 11/03/2020 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 11/06/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | 1090, 2090 APPROVED |
| 11/06/2020 | ELECTRIC - UFER | ESTEVENS | Approved | 1090 |
| 11/06/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 11/06/2020 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
| 11/09/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 11/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | |
| 11/10/2020 | PLUMBING - FINAL | TTREMBULAK | Approved | |
| 11/10/2020 | BUILDING - FINAL | TTREMBULAK | Approved | |
| 11/12/2020 | FIRE SPKLR - FINAL | jfordney | Approved |