Permit: T20CM00686
Permit Details
Apply Date:
01/29/2020
Applicant:
METRO TUCSON EXPEDITING DEVELOPMENT
Description:
E - TI BATHROOMS; REPLACE HVAC
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T20CM00686
Permit Status: L of c
Permit Description: E - TI BATHROOMS; REPLACE HVAC
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2021 | 3RD PARTY REVIEW - REVISION/OTHER | 02/05/2021 | COMPLETED |
| 01/29/2020 | PLANS OK TO SUBMIT - COMM | 02/03/2020 | COMPLETED |
| 02/03/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 03/10/2020 | COMPLETED |
| 03/10/2020 | POST 3RD PARTY REVIEW | 04/09/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00686
Permit Status: L of c
Permit Description: E - TI BATHROOMS; REPLACE HVAC
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM00686
Permit Description: E - TI BATHROOMS; REPLACE HVAC
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Not ready. Matt at 904-2219 with Diversified, project manager. Please schedule inspections from your development package permit. |
| 04/09/2021 | FIRE - FINAL | jfordney | Approved | |
| 04/09/2021 | FIRE - ALARM FINAL | jfordney | Approved | |
| 04/09/2021 | FIRE SPKLR - FINAL | jfordney | Approved | |
| 04/09/2021 | MECHANICAL - ABOVE CEILING | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - GAS PRESS TEST FNL | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - ABOVE CEILING | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - INTERMEDIATE | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - PRE SLAB | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - ROUGH, SOIL | aquiroz | Approved | |
| 04/09/2021 | ELECTRIC - FINAL | aquiroz | Approved | |
| 04/09/2021 | ELECTRIC - ABOVE CEILING | aquiroz | Approved | |
| 04/09/2021 | ELECTRIC - INTERMEDIATE | aquiroz | Approved | |
| 04/09/2021 | BUILDING - FINAL | aquiroz | Approved | |
| 04/09/2021 | BUILDING ABOVE CEILING | aquiroz | Approved | |
| 04/09/2021 | FRAMING | aquiroz | Approved | |
| 04/09/2021 | ROOF NAILING | aquiroz | Approved | |
| 04/09/2021 | MECHANICAL - FINAL | aquiroz | Approved | |
| 04/09/2021 | MECHANICAL - INTERMEDIATE | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - FINAL | aquiroz | Approved | |
| 04/09/2021 | PLUMBING - GAS PRESSURE TEST | aquiroz | Approved |