Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Address NEW:
9042 E MAPLE LEAF DR
Apply Date:
01/28/2020
Applicant:
Kevin BREAN
Description:
NEW SFR

Permit Reviews

Permit Number - T20CM00641
Permit Status: Issued
Permit Description: NEW SFR
Start Date Submittal Complete Date Status  
01/28/2020 PLANS OK TO SUBMIT - RES 01/28/2020 COMPLETED Review Details
01/28/2020 RESIDENTIAL - BLDG/WWM 09/21/2020 COMPLETED Review Details
09/28/2020 RESUBMITTAL 10/29/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM00641
Permit Status: Issued
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 2
Date Name
01/28/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
02/25/2020 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)

Conditions

Permit Number - T20CM00641
Permit Status: Issued
Permit Description: NEW SFR
Date Description Comments
01/24/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Issued
Permit Number: T20CM00641
Permite Description: NEW SFR
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/17/2023 COT - RSEL - Construction Power N/A Not Applicable

Completed Inspections

Permit Status: Issued
Permit Number: T20CM00641
Permit Description: NEW SFR
Total Completed Inspections - 23
Date Description Inspector Results Comments
01/12/2021 COT - RSPL - Yard Water Line Passed {Activity date: 01/12/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
01/12/2021 COT - RSPL - Sewer Passed {Activity date: 01/12/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
01/12/2021 COT - RSPL - Rough Soil Passed {Activity date: 01/12/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
02/18/2021 COT - RSBU - Preslab Passed {Activity date: 02/18/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved}
02/18/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 02/18/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved}
06/11/2021 COT - RSBU - Roof Nailing Passed {Activity date: 06/11/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } ; {Activity date: 02/25/2020; Status: Prior to Intermediates; Inspector: KEN; Comment: Entered by KKARSEN1 - ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION}
09/17/2021 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

}
09/17/2021 COT - LCBU - Framing Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

} ; {Activity date: 06/11/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - }
09/17/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

}
09/17/2021 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

} ; {Activity date: 09/09/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval please add H.25 at all truss bearing points and RSP4 at studs on exterior walls

}
09/17/2021 RSEL - Electrical Progress Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

}
09/17/2021 RSME - Mechanical Progress Passed {Activity date: 09/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1025, 1035, 2035, 3035, 4035, 1080. Approved.

}
11/24/2021 COT - HCBU - Interior Shear Bracing Passed {Activity date: 11/24/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
12/16/2022 COT - RSEL - Electrical Underground Passed
12/16/2022 COT - RSEL - Grounding/Bonding Passed Ufer
12/16/2022 BULD - Electrical Clearance Passed Approved, INCR clearance is required
09/26/2023 COT - RSPL - Gas Pressure Test Passed
09/26/2023 COT - BULD - SWG Clearance Passed Approved connections, SWG Clearance is required for the meter set
11/13/2023 COT - RSPL - Plumbing Final Passed
11/17/2023 COT - RSME - Mechanical Final Passed
11/17/2023 COT - RSEL - Outdoor Lighting Passed
11/17/2023 COT - RSEL - Electrical Final Passed
11/17/2023 RSBU - Building Final Passed

Documents

File Name Document Type  
PLAN REVIEW CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
BREAN CORRECTIONS.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
STRUCTURAL CALS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW