Permit: T20CM00486
Permit Details
Apply Date:
01/22/2020
Applicant:
TAZMINE KHATRI
Description:
CLUB HOUSE/THEATER
Contractors:
- TOFEL CONSTRUCTION LLC
Permit Reviews
Permit Number - T20CM00486
Permit Status: C of o
Permit Description: CLUB HOUSE/THEATER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2020 | PLANS OK TO SUBMIT - COMM | 01/27/2020 | COMPLETED |
| 01/27/2020 | COMMERCIAL - TI | 05/12/2020 | COMPLETED |
| 05/12/2020 | RESUBMITTAL | 07/20/2020 | COMPLETED |
| 07/20/2020 | RESUBMITTAL | 09/10/2020 | COMPLETED |
| 12/21/2020 | REVISION - - 1ST | 02/26/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00486
Permit Status: C of o
Permit Description: CLUB HOUSE/THEATER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/22/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM00486
Permit Description: CLUB HOUSE/THEATER
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/23/2020 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Approved. “Stable” building waste and vent lines (2”-4”) throughput structure. Ok to back fill progress areas. |
| 11/23/2020 | BUILDING PRE-SLAB | JBURGE | Approved | Partial. Kitchen, restroom, and porch area slabs. Ok to place concrete in progress areas |
| 11/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Partial. West and South wall footing of theatre. Ok to place concrete in progress area. |
| 12/21/2020 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | Ap Final lift of theater walls ok to grout. |
| 01/22/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | APPROVED |
| 01/22/2021 | FRAMING | JBURGE | Approved | APPROVED BUILDING E AND THEATER N OK TO INSULATE AND COVER WALLS IN BUILDING E ONLY |
| 02/05/2021 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | APPROVED, OK TO INSULATE AND COVER CEILINGS |
| 02/05/2021 | PLUMBING - ABOVE CEILING | JBURGE | Approved | APPROVED, OK TO INSULATE AND COVER CEILINGS |
| 02/05/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | APPROVED, OK TO INSULATE AND COVER CEILINGS |
| 02/05/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | APPROVED, OK TO INSULATE AND COVER CEILINGS |
| 04/13/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO/INCR/METER SETS FOR PANEL A, B, D AND LEASE SPACE A1 FOR BUILDING E AND THEATER ADDITION |
| 04/13/2021 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | |
| 06/14/2021 | MECHANICAL - PROGRESS | JBURGE | Approved | |
| 06/14/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 06/14/2021 | PLUMBING - PROGRESS | JBURGE | Approved | |
| 06/14/2021 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
| 06/14/2021 | PLUMBING - PRE SLAB | JBURGE | Approved | |
| 06/14/2021 | ELECTRIC - PROGRESS | JBURGE | Approved | |
| 06/14/2021 | ELECTRIC - TEMPORARY SERVICE | JBURGE | Approved | |
| 06/14/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
| 06/14/2021 | ELECTRIC - UFER | JBURGE | Approved | |
| 06/14/2021 | BUILDING - PROGRESS | JBURGE | Approved | |
| 06/14/2021 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 06/14/2021 | ROOF NAILING | JBURGE | Approved | |
| 06/14/2021 | NPPO - FINAL | JBURGE | Approved | |
| 06/14/2021 | SIGN - FINAL | JBURGE | Approved | |
| 06/18/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 06/18/2021 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/18/2021 | RIGHT OF WAY - FINAL | Bravin | Approved | no ROW inspection needed. |
| 09/02/2021 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
| 09/07/2021 | PLUMBING - FINAL | RSHERRY | Approved | |
| 09/07/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 10/01/2021 | BUILDING - FINAL | JBURGE | Approved | Approved. Pending Fire Finals |
| 10/07/2021 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 10/07/2021 | FIRE - ALARM FINAL | MRoss | Approved | |
| 10/15/2021 | FIRE - FINAL | CBASALDUA | Approved |