Permit Number - T20CM00250
Permit Status: Issued
Permit Description: NEW CARPORT, SHED, PORCH & REMODEL SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/13/2020 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/14/2021 | COMPLETED |
04/14/2021 | RESUBMITTAL | 05/18/2021 | COMPLETED |
05/18/2021 | RESUBMITTAL | 05/27/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00250
Permit Status: Issued
Permit Description: NEW CARPORT, SHED, PORCH & REMODEL SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/13/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T20CM00250
Permite Description: NEW CARPORT, SHED, PORCH & REMODEL SFR
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - LCBU - Framing | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Issued
Permit Number: T20CM00250
Permit Description: NEW CARPORT, SHED, PORCH & REMODEL SFR
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/26/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/26/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/25/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
09/03/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/03/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Three inch waste line to main sewer line. Ok to cover progress areas.} ; {Activity date: 09/01/2021; Status: Denied; Inspector: RCHANDLER; Comment: Entered by VVERA1 - DE. Provide water test for DWV system.} | |
09/14/2021 | COT - RSBU - Stem Wall/Retaining Wall | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VVERA1 - AP} | |
01/18/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/14/2021; Status: Cancelled; Inspector: RELEFANTE; Comment: Entered by VVERA1 - 1025 wrong code called in} | |
03/10/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 03/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
04/08/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/08/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Meter to house.} |
|
04/08/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 04/08/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Underground conduit ok to backfill.} |
|
04/22/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
04/22/2022 | RSME - Mechanical Progress | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
04/22/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 01/19/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Underground portion only. Sent text at 8:51 8:52; got return text from contractor inquiring which job I was asking about. 8:55; sent address to contractor via text. 8:58; got return text inquiring which inspection was scheduled} |
|
02/23/2023 | COT - RSME - Mechanical Final | Passed | ||
02/23/2023 | RSBU - Building Final | Passed | ||
02/23/2023 | COT - RSPL - Plumbing Final | Passed | ||
02/23/2023 | COT - RSEL - Electrical Final | Passed |