Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address NEW:
4900 E SPEEDWAY BL
Apply Date:
11/04/2019
Applicant:
B & F CONTRACTING INC
Description:
SEWER REHABILITATION - NO EXCAVATION INSTALLATION OF APPROXIMATELY 388 LF OF 8" CIPP, BETWEEN MH 8818-01 AND MH 8818*01. TRAFFIC CONTROL WILL BE A RIGHT LANE CLOSURE IN THE AREA OF SPEEDWAY AND N ARCADIA AV., AS SHOWN ON THE SITE AND TCP MG #8818-01 WILL HAVE A NEW CONCRETE COLLAR INSTALLED AND A BENCH REHABILITATION PERFORMED. C/O #8188*01 WILL ALSO BE REMOVED AND REPLACED WITH A NEW TERMINAL MANHOLE REQUIRING A 10X10 EXCAVATION. TRAFFIC CONTROL WILL BE A RIGHT LANE CLOSURE FOR SPEEDWAY DURING THE LINING PROCESS AS WELL DURING WORK HOURS FOR THE TERMINAL MANHOLE INSTALL THE BIKE LANE WILL BE CLOSED 24 HRS A DAY DURING THE MANHOLE INSTALL ALL TRAFFIC CONTROL WILL BE MOVED TO THE EDGE OF THE BIKE LANE DURING OFF WORK HOURS. BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 FOR COORDINATION. ** Permit end date has been modified due to holiday restriction beginning November 28, 2019 - January 2, 2020.
Contractors:
  • HOFFMAN PROFESSIONAL PIPE SERVICES
  • OLSON PRECAST STRUCTURES

Completed Inspections

Permit Status: Final
Permit Number: T19RW06761
Permit Description: SEWER REHABILITATION - NO EXCAVATION INSTALLATION OF APPROXIMATELY 388 LF OF 8" CIPP, BETWEEN MH 8818-01 AND MH 8818*01. TRAFFIC CONTROL WILL BE A RIGHT LANE CLOSURE IN THE AREA OF SPEEDWAY AND N ARCADIA AV., AS SHOWN ON THE SITE AND TCP MG #8818-01 WILL HAVE A NEW CONCRETE COLLAR INSTALLED AND A BENCH REHABILITATION PERFORMED. C/O #8188*01 WILL ALSO BE REMOVED AND REPLACED WITH A NEW TERMINAL MANHOLE REQUIRING A 10X10 EXCAVATION. TRAFFIC CONTROL WILL BE A RIGHT LANE CLOSURE FOR SPEEDWAY DURING THE LINING PROCESS AS WELL DURING WORK HOURS FOR THE TERMINAL MANHOLE INSTALL THE BIKE LANE WILL BE CLOSED 24 HRS A DAY DURING THE MANHOLE INSTALL ALL TRAFFIC CONTROL WILL BE MOVED TO THE EDGE OF THE BIKE LANE DURING OFF WORK HOURS. BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 FOR COORDINATION. ** Permit end date has been modified due to holiday restriction beginning November 28, 2019 - January 2, 2020.
Total Completed Inspections - 1
Date Description Inspector Results Comments
01/15/2020 TDOT-EXCAV GENERAL INSPECTION MVV Approved Completed. Concrete collars installed, roadway repaired.

Documents

File Name Document Type  
T19RW06761.PDF ROW-RIGHT OF WAY VIEW