Permit: T19RW06337
Permit Details
Apply Date:
10/21/2019
Applicant:
K E & G CONSTRUCTION ***APA***
Description:
Installation of 365LF of 8-inch CIPP Lining between manholes 9837* 01 and 9837-11. Provide MH rehabilitation and install new collars for manholes 9887-11. A one day 24-hour closure required for manhole collars to cure. Installing terminal manhole at 9837 * 01. ** ABUTTING PROPERTY WILL NEED TO BE NOTIFED OF WORK 10/21/2019-PLAN CHANGE- REMOVE AND REPLACE 21 LF OF 8" SEWER MAIN
Contractors:
- PROPIPE PROFESSIONAL PIPE SERVICE
Completed Inspections
Permit Status: Final
Permit Number: T19RW06337
Permit Description: Installation of 365LF of 8-inch CIPP Lining between manholes 9837* 01 and 9837-11. Provide MH rehabilitation and install new collars for manholes 9887-11. A one day 24-hour closure required for manhole collars to cure. Installing terminal manhole at 9837 * 01.
** ABUTTING PROPERTY WILL NEED TO BE NOTIFED OF WORK
10/21/2019-PLAN CHANGE-
REMOVE AND REPLACE 21 LF OF 8" SEWER MAIN
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | Pipe has been relinned and bench work finished in manhole. New concrete collars have been added to the existing MH. no issues or repairs needed in alley. |