Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address NEW:
3050 S M L KING JR WY
Apply Date:
09/27/2019
Applicant:
SOLON CORPORATION ***APA***
Description:
OPEN TRENCH EXCAVATION FOR INSTALLATION OF NEW 4-INCH ELECTRICAL CONDUIT (1 EACH), APPROX. 100 FEET ABOVE EXISTING BOX CULVERT IN ORDER TO CONNECT FUTURE COMMS. CONDUIT AREA FROM NEW GEICO HQ'S TO NEW/ FUTURE TEP KINO SUBSTATION.

Completed Inspections

Permit Status: Final
Permit Number: T19RW05676
Permit Description: OPEN TRENCH EXCAVATION FOR INSTALLATION OF NEW 4-INCH ELECTRICAL CONDUIT (1 EACH), APPROX. 100 FEET ABOVE EXISTING BOX CULVERT IN ORDER TO CONNECT FUTURE COMMS. CONDUIT AREA FROM NEW GEICO HQ'S TO NEW/ FUTURE TEP KINO SUBSTATION.
Total Completed Inspections - 1
Date Description Inspector Results Comments
10/10/2019 TDOT-EXCAV GENERAL INSPECTION Bravin Approved 100 ft of 4in conduit was installed, with a concrete cap over the pipe that is on top of existing box culvert. TEPs request. No traffic contol used because job was completed inside a existing Borderland job. No issues or further repairs needed