Permit: T19RW05496
Permit Details
Apply Date:
09/21/2019
Applicant:
SOUTHWEST GAS
Description:
2 5X5 bellholes dirt/blktop----- to repair/replace gas line NOTES: Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. OTHER PROJECTS/ACTIVITIES ACTIVE IN AREA, AS A CONTRACTOR YOU MUST COORDINATE WITH EXISTING TRAFFIC CONTROLE AND WORKERS. This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Allison Diehl at allison.diehl@tucsonaz.gov with any questions.
Contractors:
- ARIZONA PIPELINE COMPANY
- NATIONAL BARRICADE LLC
- NORTHERN PIPELINE CONSTRUCTION C
Completed Inspections
Permit Status: Final
Permit Number: T19RW05496
Permit Description: 2 5X5 bellholes dirt/blktop----- to repair/replace gas line
NOTES:
Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced.
OTHER PROJECTS/ACTIVITIES ACTIVE IN AREA, AS A CONTRACTOR YOU MUST COORDINATE WITH EXISTING TRAFFIC CONTROLE AND WORKERS.
This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Allison Diehl at allison.diehl@tucsonaz.gov with any questions.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | all gas work complete. Permit will be closed because Russell is in negotiations about repave. The builder agrees that all of Russell needs repair. No C of Os will be sighned off on until repairs are made on Russell |