Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address:
442 N CHURCH AV
Apply Date:
09/13/2019
Applicant:
SOUTHWEST GAS
Description:
INSTALL NEW 147' 6" STEEL AND 143' OF 4" GDB50 IN JOINT TRENCH ON 5TH ST. INSTALL 370' 2" GDB50 BY BORE ALONG PERRY AV AND 203' OF GAS LINE SERVICE IN ROW. PERFORM MAIN ABANDONMENT IN DIRECT CONFLICT WITH THE DOWNTOWN LINKS PROJECT. CIP PROJECT DOWNTOWN LINKS 6TH ST UNDERPASS TO BROADWAY BL PIA S30N WORK ORDER # 3056813 ADDRESS ON APPLICATION- 6TH ST/CHURCH AV - VARIOUS LOCATIONS. This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Allison Diehl at allison.diehl@tucsonaz.gov with any questions.

Completed Inspections

Permit Status: Final
Permit Number: T19RW05182
Permit Description: INSTALL NEW 147' 6" STEEL AND 143' OF 4" GDB50 IN JOINT TRENCH ON 5TH ST. INSTALL 370' 2" GDB50 BY BORE ALONG PERRY AV AND 203' OF GAS LINE SERVICE IN ROW. PERFORM MAIN ABANDONMENT IN DIRECT CONFLICT WITH THE DOWNTOWN LINKS PROJECT. CIP PROJECT DOWNTOWN LINKS 6TH ST UNDERPASS TO BROADWAY BL PIA S30N WORK ORDER # 3056813 ADDRESS ON APPLICATION- 6TH ST/CHURCH AV - VARIOUS LOCATIONS. This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Allison Diehl at allison.diehl@tucsonaz.gov with any questions.
Total Completed Inspections - 1
Date Description Inspector Results Comments
09/16/2019 TDOT-EXCAV GENERAL INSPECTION DR Approved Precon with NPL and SWG. Will begin 9/17 on first 2 services. Will have meeting before proceeding with High Pressure on Stone Av.

Documents

File Name Document Type  
T19RW05182.PDF ROW-RIGHT OF WAY VIEW
T19RW05182 R1.PDF ROW-RIGHT OF WAY VIEW
T19RW05182.PDF ROW-RIGHT OF WAY VIEW