Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19RW03491
Permit Details
Apply Date:
06/18/2019
Applicant:
COX COMMUNICATIONS
Description:
Continuing from out of row (535 E 16th St ) 35' overlash to TEP pole, riser down and begin 171' bore/ trench heading NE, place 3x3 pothole and place new COX vault, continue 66' bore/trench heading SE and place 3x3 pothole and new COX vault, tie in .
Contractors:
- MEARS GROUP INC
- TRUENET COMMUNICATIONS CORP
Outstanding Inspections
Permit Status: Final
Permit Number: T19RW03491
Permite Description: Continuing from out of row (535 E 16th St ) 35' overlash to TEP pole, riser down and begin 171' bore/ trench heading NE, place 3x3 pothole and place new COX vault, continue 66' bore/trench heading SE and place 3x3 pothole and new COX vault, tie in .
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
FIRE INSP - OPERATIONAL PERMIT | N/A | Not Inspected |
Completed Inspections
Permit Status: Final
Permit Number: T19RW03491
Permit Description: Continuing from out of row (535 E 16th St ) 35' overlash to TEP pole, riser down and begin 171' bore/ trench heading NE, place 3x3 pothole and place new COX vault, continue 66' bore/trench heading SE and place 3x3 pothole and new COX vault, tie in .
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin/Meist | Approved | overlash and boring and trenching all competed, area looked clean and had no issues or repairs needed. |
01/31/2020 | FIRE INSP - CONSTRUCTION PERMI | Bravin | Approved | ABC---new vault on Toole, no issues with boring or overlash. Permit complete |