Permit: T19RW01292
Permit Details
Apply Date:
03/11/2019
Applicant:
MCMANUS CONSTRUCTION
Description:
STONE: TIE IN TO EXISTING APPROACH. INSTALL 24 CURB AND 35 LF SIDEWALK. SPEEDWAY: 1. REMOVE APPROX 70 LF OF EXISTING SIDEWALK AND REPLACE WITH 100 LF NEW SIDEWALK. 2. REMOVE APROX 29 LF EXISTING CURB AND REPLACE WITH APPROX 105 LF NEW CURB. 3. REMOVE TWO 24 FT APPROACHES AND REPLACE WITH THREE NEW ADA RAMPS. ALL OF THE ABOVE WILL BE PER PAG STANDARD DETAILS AND PER DP17-0154 NOTE: SPEEDWAY BL AND STONE AVE ARE UNDER PAVEMENT MORATORIUM - ANY CUTS IN THE ASPHALT WILL REQUIRE A 2" MILL AND OVERLAY FOR 50' FROM THE OUTSIDE OF THE CUT FOR ALL AFFECTED TRAVEL LANES
Contractors:
- BOYD CONTRACTING L L C
- COPPER HILL CONSTRUCTION INC
Completed Inspections
Permit Status: Final
Permit Number: T19RW01292
Permit Description: STONE: TIE IN TO EXISTING APPROACH. INSTALL 24 CURB AND 35 LF SIDEWALK.
SPEEDWAY:
1. REMOVE APPROX 70 LF OF EXISTING SIDEWALK AND REPLACE WITH 100 LF NEW SIDEWALK.
2. REMOVE APROX 29 LF EXISTING CURB AND REPLACE WITH APPROX 105 LF NEW CURB.
3. REMOVE TWO 24 FT APPROACHES AND REPLACE WITH THREE NEW ADA RAMPS.
ALL OF THE ABOVE WILL BE PER PAG STANDARD DETAILS AND PER DP17-0154
NOTE: SPEEDWAY BL AND STONE AVE ARE UNDER PAVEMENT MORATORIUM - ANY CUTS IN THE ASPHALT WILL REQUIRE A 2" MILL AND OVERLAY FOR 50' FROM THE OUTSIDE OF THE CUT FOR ALL AFFECTED TRAVEL LANES
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2019 | TDOT-EXCAV GENERAL INSPECTION | DR | Approved | Work complete. ADA tie in rempved and replaced per Engineer. |