Permit: T19CM09238
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
2555 E CALLE TOBO
Address NEW:
2555 E CALLE TOBO
Apply Date:
12/16/2019
Applicant:
Description:
SFR DRHOX30E19 T19-M0164
Permit Reviews
Permit Number - T19CM09238
Permit Status: Expired
Permit Description: SFR DRHOX30E19 T19-M0164
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/28/2020 | REVISION - - 1ST | 04/28/2020 | ACTIVE |
| 12/16/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM09238
Permit Status: Expired
Permit Description: SFR DRHOX30E19 T19-M0164
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 12/16/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 12/16/2019 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM09238
Permit Description: SFR DRHOX30E19 T19-M0164
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/10/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 01/15/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 01/15/2020 | COT - RSBU - Preslab | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 01/15/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 01/15/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 01/15/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 02/07/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/07/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 02/07/2020 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 02/07/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/04/2020 | COT - LCBU - Framing | Passed | {Activity date: 03/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - } ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/04/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 03/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - } | |
| 03/04/2020 | RSME - Mechanical Progress | Passed | {Activity date: 03/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - } ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/04/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 03/04/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - CLEAR GAS} ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/06/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 03/06/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } ; {Activity date: 03/04/2020; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - } ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/06/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 03/06/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } ; {Activity date: 03/04/2020; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - Provide DWV and water pressure test.} ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/06/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/06/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } ; {Activity date: 02/28/2020; Status: Cancelled; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
| 03/17/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 03/17/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by SFLORES2 - } | |
| 04/01/2020 | COT - RSPL - Sewer | Passed | {Activity date: 04/01/2020; Status: Approved; Inspector: GALLAGHER; Comment: Entered by SFLORES2 - RVI} | |
| 05/06/2020 | COT - RSME - Mechanical Final | Passed | {Activity date: 05/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
| 05/06/2020 | RSBU - Building Final | Passed | {Activity date: 05/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
| 05/06/2020 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 05/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
| 05/06/2020 | COT - RSPL - Plumbing Final | Passed | {Activity date: 05/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } ; {Activity date: 12/16/2019; Status: Prior to Final Inspectn; Inspector: GERRYGAZIOLI; Comment: Entered by AMARTIN1 - PLUMBING FINAL- P2F- P19WX02925 - NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PUBLIC SEWER G-2018-096 IS ACCEPTED AND RELEASED BY PCRWRD} | |
| 05/06/2020 | COT - RSEL - Electrical Final | Passed | {Activity date: 05/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } |