Permit: T19CM08948
Permit Details
Apply Date:
12/05/2019
Applicant:
RAMON VALDEZ
Description:
NEW SFRS VALD000119 T19-M003
Contractors:
- JV'S ENTERPRISES
Permit Reviews
Permit Number - T19CM08948
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/05/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08948
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/05/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08948
Permit Description: NEW SFRS VALD000119 T19-M003
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | RVI |
| 12/12/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | RVI |
| 12/13/2019 | ELECTRIC - UFER | DQUINN | Approved | RVI |
| 12/13/2019 | BUILDING PRE-SLAB | DQUINN | Approved | RVI |
| 12/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | RVI |
| 12/23/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 12/23/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 12/27/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 12/27/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 12/27/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 12/27/2019 | FRAMING | DQUINN | Approved | |
| 12/30/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 12/30/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
| 03/31/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 03/31/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 03/31/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 03/31/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 03/31/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 03/31/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
| 04/01/2020 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | NEW 3" ABS FROM HOUSE TO HCS OK TO BACK FILL |