Permit: T19CM08887
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
380 E FORT LOWELL RD
Address NEW:
380 E FORT LOWELL RD
Apply Date:
12/04/2019
Applicant:
ERIN HASTREITER
Description:
TI: MEDICAL OUTPATIENT
Architects:
- SWAN WAYNE E
Contractors:
- CAMWEST GROUP INC
Permit Reviews
Permit Number - T19CM08887
Permit Status: L of c
Permit Description: TI: MEDICAL OUTPATIENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/04/2019 | COMMERCIAL - TI | 01/30/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08887
Permit Status: L of c
Permit Description: TI: MEDICAL OUTPATIENT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/04/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM08887
Permit Description: TI: MEDICAL OUTPATIENT
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 02/14/2020 | FRAMING | BSTEVENS | Approved | RVI |
| 02/14/2020 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | RVI |
| 02/18/2020 | ENGINEERING - FINAL | DROBERTS | Approved | PENDING ALL OTHER INSPECTIONS. THS PARKING LOT EAST OF THIS SITE WAS NOT CONSTRUCTED PER THE APPROVED PLANS AND STILL REMAINS IN AN EXPIRED STATUS AT THIS TIME. |
| 02/18/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 02/18/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
| 02/18/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 02/18/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 02/18/2020 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 02/18/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 03/09/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 03/09/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 03/09/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 04/03/2020 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
| 04/03/2020 | ELECTRIC - FINAL | DQUINN | Approved | |
| 04/03/2020 | MECHANICAL - FINAL | DQUINN | Approved | |
| 04/13/2020 | BUILDING - FINAL | RSHERRY | Approved |