Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
5470 E LITTLETOWN RD
Apply Date:
12/04/2019
Applicant:
LECHNER CONSTRUCTION INC , ***APA***
Description:
NEW RETAIL BUILDING
Contractors:
  • LECHNER CONSTRUCTION INC , ***APA***

Permit Reviews

Permit Number - T19CM08884
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Start Date Submittal Complete Date Status  
03/02/2020 RESUBMITTAL - TI ALL 04/16/2020 COMPLETED Review Details
04/16/2020 RESUBMITTAL 04/30/2020 COMPLETED Review Details
04/30/2020 RESUBMITTAL 05/07/2020 COMPLETED Review Details
12/17/2019 COMMERCIAL - NEW 03/02/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM08884
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
Date Name
12/04/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM08884
Permit Description: NEW RETAIL BUILDING
Total Completed Inspections - 30
Date Description Inspector Results Comments
05/08/2020 ELECTRIC - TEMPORARY SERVICE DMUNIZ Approved Clear TEP TMPP
05/12/2020 PLUMBING - ROUGH, SOIL DMUNIZ Approved
05/18/2020 BUILDING PRE-SLAB TTREMBULAK Approved
06/04/2020 SITE - SEWER DMUNIZ Approved
06/04/2020 PLUMBING - YARD WTR LINE/TEST DMUNIZ Approved
06/26/2020 ELECTRIC - INTERMEDIATE DMUNIZ Approved Approved
06/26/2020 FRAMING DMUNIZ Approved Approved
06/26/2020 EXT METAL CLIPS/EXT SHEATHING DMUNIZ Approved Approved
07/06/2020 MECHANICAL - INTERMEDIATE DMUNIZ Approved Approved, Mechanical Ducts to stock room and Bathrooms Inspected, RTU’s Installed.
07/06/2020 BUILDING - PROGRESS DMUNIZ Approved Approved, Insulation in Exterior & Interior walls Inspected ok to to proceed.
07/07/2020 PLUMBING - INTERMEDIATE TTREMBULAK Approved Approved. Ok for drywall
07/22/2020 PLUMBING - SEWER HCS CONNECT DMUNIZ Approved Approved
07/24/2020 U VALUE FOR WINDOW TTREMBULAK Approved Approved
07/24/2020 BUILDING ABOVE CEILING TTREMBULAK Approved Approved
07/29/2020 ELECTRIC - SERVICE UPGRADE DMUNIZ Approved NOT APPLICABLE.
07/29/2020 ELECTRIC - CONSTRUCTION POWER DMUNIZ Approved Approved clear TEP ECO
07/29/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved Approved, Electrical conduits for Site lighting ok to backfill and proceed.
07/29/2020 ELECTRIC - UFER DMUNIZ Approved Approved, Grounding for Site lighting inspected.
07/29/2020 EXCAVATION/LAYOUT REBAR & ZON DMUNIZ Approved Approved- Excavation for footings and Inspection of Rebar case-ons for site lighting ok for concrete placement.
08/04/2020 TEP CLEARANCE - PM DMUNIZ Approved CODE ECO
08/26/2020 PLUMBING - BACK WATER VALVE DMUNIZ Approved Approved
08/26/2020 ELECTRIC - FINAL DMUNIZ Approved Approved
08/26/2020 ELECTRIC - OUTDOOR LIGHTING DMUNIZ Approved Approved
08/26/2020 BUILDING - FINAL DMUNIZ Approved Approved
08/27/2020 FIRE - FINAL MRoss Approved -Provide front door key to put in Fire Department Knox Box
-Panic hardware to be installed on rear doors (not completed yet)
08/27/2020 OUTDOOR LIGHTING FINAL TTREMBULAK Approved Cancelled. * This was approved yesterday. NOTE; 2099 DID NOT SHOW AP, CHANGED TO AP WITH THIS ENTRY. (RS)
08/28/2020 PLUMBING - FINAL DMUNIZ Approved Approved, water reports submitted.
09/17/2020 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
09/17/2020 ENGINEERING - FINAL RLEDONNE Approved Approved
09/18/2020 CERTIFICATE OF OCCUPANCY JG3 Approved

Documents

File Name Document Type  
SPECIAL INSPECTION REPORTS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
T19CM08884 - TCO 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SPECIAL INSPECTION REPORTS.PDF DOCUMENTS VIEW
T19CM08884 - TCO.PDF DOCUMENTS VIEW
T19CM08884 AIR BALANCE.PDF DOCUMENTS VIEW
T19CM08884 WATER REPORT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
1 - COT PERMIT APPLICATION.PDF DOCUMENTS VIEW
1 - COT ZONING CONDITIONS.PDF DOCUMENTS VIEW
1 - FAA AND AVIGATION EASEMENT.PDF DOCUMENTS VIEW
3_COMMENT RESPONSE PLUMBING #2.PDF DOCUMENTS VIEW
REV-1_ METAL BUILDING E SHEETS.PDF CONSTRPLANS VIEW
REV-1_ PERMIT SET REV.PDF CONSTRPLANS VIEW
REV-1_ SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
REV-1_HVAC_LOAD_CALCULATIONS.PDF DOCUMENTS VIEW
REV-1-CALCULATION PACKAGE.PDF DOCUMENTS VIEW
SS_F1.PDF DOCUMENTS VIEW
SS_F2.PDF DOCUMENTS VIEW
SS_F3.PDF DOCUMENTS VIEW
SS_F4.PDF DOCUMENTS VIEW