Permit: T19CM08858
Permit Details
Apply Date:
12/03/2019
Applicant:
CHRIS ROYER - SOVEREIGN ELECTRIC L L C ,
Description:
UPGRADE UP TO 400AMPS
Contractors:
- SOVEREIGN ELECTRIC L L C ,
Permit Reviews
Permit Number - T19CM08858
Permit Status: Closed
Permit Description: UPGRADE UP TO 400AMPS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/31/2020 | RESUBMITTAL | 08/10/2020 | COMPLETED |
| 12/03/2019 | WALK THRU - COMM | 02/19/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08858
Permit Status: Closed
Permit Description: UPGRADE UP TO 400AMPS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/03/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Closed
Permit Number: T19CM08858
Permit Description: UPGRADE UP TO 400AMPS
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER UNITS 1650, 1652, 1654, 1656, 1658, 1660, & 1662 |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE UNITS 1650, 1652, 1654, 1656, 1658, 1660, 1662 INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved |
| 08/28/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE INCR/CUTOVER |
| 08/28/2020 | ELECTRIC - SERVICE UPGRADE | TTREMBULAK | Approved | Approved Clearance for TEP INCR connect ok (cutover). Units 1650, 1652, 1654, 1656, 1658, 1660, & 1662 ( seven meters total). |