Permit: T19CM08753
Permit Details
Apply Date:
11/26/2019
Applicant:
Rafael R Ghinis
Description:
NEW SFR
Permit Reviews
Permit Number - T19CM08753
Permit Status: Issued
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/24/2020 | REVISION - - 1ST | 02/24/2020 | COMPLETED |
11/26/2019 | PLANS OK TO SUBMIT - RES | 11/27/2019 | COMPLETED |
11/27/2019 | RESIDENTIAL - BLDG/WWM | 12/11/2019 | COMPLETED |
12/11/2019 | RESUBMITTAL | 12/20/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08753
Permit Status: Issued
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
11/26/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
11/27/2019 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
11/27/2019 | FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
Conditions
Permit Number - T19CM08753
Permit Status: Issued
Permit Description: NEW SFR
Date | Description | Comments |
---|---|---|
12/09/2019 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Completed Inspections
Permit Status: Issued
Permit Number: T19CM08753
Permit Description: NEW SFR
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 12/23/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} | |
01/06/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} | |
01/06/2020 | COT - RSBU - Preslab | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} | |
01/06/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} | |
02/28/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/28/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 02/14/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by SFLORES2 - Submit copy of truss plans to city.} ; {Activity date: 02/12/2020; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Shall provide access to the roof at the time of inspection request 2- Shall provide the approved truss calls on site at the time of inspection request.} ; {Activity date: 02/11/2020; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Canceled} ; {Activity date: 12/09/2019; Status: Prior to Intermediates; Inspector: KEN; Comment: Entered by KKARSEN1 - ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION} ; {Activity date: 12/09/2019; Status: Prior to Intermediates; Inspector: KEN; Comment: Entered by KKARSEN1 - ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION} |
|
02/28/2020 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 02/28/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 02/14/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by SFLORES2 - Missing Simpson clip on porch post, missing nails in shear walls at windows, tighten hold down nuts.} ; {Activity date: 02/12/2020; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Shall provide access to the roof at the time of inspection request 2- Shall provide the approved truss calls on site at the time of inspection request.} ; {Activity date: 02/11/2020; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Canceled} |
|
03/02/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/02/2020; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - } | |
03/16/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 03/16/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by SFLORES2 - mechanical; electrical, plumbing} ; {Activity date: 03/11/2020; Status: Denied; Inspector: ESTEVENS; Comment: Entered by SFLORES2 - Not all electrical boxes wired, S-trap at washer drain, DWV is jot under test. STOPPED INSPECTION.} | |
03/16/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 03/16/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by SFLORES2 - } ; {Activity date: 03/11/2020; Status: Denied; Inspector: ESTEVENS; Comment: Entered by SFLORES2 - Not all electrical boxes wired, S-trap at washer drain, DWV is jot under test. STOPPED INSPECTION.} | |
03/16/2020 | RSME - Mechanical Progress | Passed | {Activity date: 03/16/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by SFLORES2 - } ; {Activity date: 03/11/2020; Status: Denied; Inspector: ESTEVENS; Comment: Entered by SFLORES2 - Not all electrical boxes wired, S-trap at washer drain, DWV is jot under test. STOPPED INSPECTION.} | |
04/30/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/30/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - CODE ECO} | |
04/30/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 04/30/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - RVI Clearance for TEP ECO called in to Natalie at 11:25 a.m.} | |
07/13/2020 | COT - RSME - Mechanical Final | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} | |
07/13/2020 | COT - LCBU - Framing | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} ; {Activity date: 02/11/2020; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Canceled} | |
07/13/2020 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} | |
07/13/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} | |
07/13/2020 | COT - RSPL - Plumbing Final | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - approved} | |
07/13/2020 | COT - RSEL - Electrical Final | Passed | {Activity date: 07/13/2020; Status: Approved; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - AP} | |
10/18/2022 | RSBU - Building Final | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: CTREVIL; Comment: Entered by CTREVIL1 - } ; {Activity date: 07/13/2020; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - INSPECTOR APPROVED BUILDING FINAL. PENDING TWO SPECIAL INSPECTIONS.} |