Permit: T19CM08685
Permit Details
Apply Date:
11/22/2019
Applicant:
INAI ANZUETO
Description:
EXTEND FAMILY ROOM AND ADD STUDIO
Permit Reviews
Permit Number - T19CM08685
Permit Status: Final
Permit Description: EXTEND FAMILY ROOM AND ADD STUDIO
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/28/2020 | RESUBMITTAL | 06/04/2020 | COMPLETED |
| 09/24/2020 | REVISION - - 1ST | 10/20/2020 | COMPLETED |
| 11/22/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 05/28/2020 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08685
Permit Description: EXTEND FAMILY ROOM AND ADD STUDIO
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved. |
| 10/29/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved. |
| 10/29/2020 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Not Applicable. |
| 10/29/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Not Applicable. |
| 11/09/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 11/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 12/10/2020 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 12/10/2020 | FRAMING | RCHANDLER | Approved | |
| 12/10/2020 | ROOF NAILING | RCHANDLER | Approved | |
| 09/23/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | Approved |
| 10/27/2021 | ELECTRIC - FINAL | TGAUSP | Approved | - Cancelled, no on site response |
| 11/03/2021 | RESIDENTIAL INTERMEDIATE | TGAUSP | Approved | Approved, mechanical (surface mini-split) |
| 01/21/2022 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
| 01/21/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | NA |
| 02/10/2022 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved 4090 |
| 02/10/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved 2090 |
| 02/10/2022 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 02/10/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved |