Permit Number - T19CM08534
Permit Status: Final
Permit Description: STORAGE BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/19/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08534
Permit Status: Final
Permit Description: STORAGE BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08534
Permit Description: STORAGE BLDG
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2020 | ELECTRIC - UFER | DQUINN | Approved | |
| 02/28/2020 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 02/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 03/27/2020 | ROOF NAILING | DMUNIZ | Approved | |
| 03/27/2020 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
| 04/28/2020 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | RVI The TEP clearance code is INCR. This is a cutover. |
| 04/28/2020 | ELECTRIC - PROGRESS | ESTEVENS | Approved | RVI |
| 04/28/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | RVI |
| 04/28/2020 | FRAMING | ESTEVENS | Approved | RVI |
| 05/11/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE INCR/CUTOVER |
| 05/27/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 05/27/2020 | BUILDING - FINAL | DMUNIZ | Approved |