Permit: T19CM08296
Permit Details
Apply Date:
11/08/2019
Applicant:
SUNBRIGHT SOLAR LLC **APA**
Description:
E - INSTALL ROOFTOP SOLAR SYSTEM
Contractors:
- SUNBRIGHT SOLAR LLC **APA**
Permit Reviews
Permit Number - T19CM08296
Permit Status: Final
Permit Description: E - INSTALL ROOFTOP SOLAR SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/08/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 11/14/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08296
Permit Status: Final
Permit Description: E - INSTALL ROOFTOP SOLAR SYSTEM
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 11/08/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 11/08/2019 | THE INSTALLATION SHALL COMPLY WITH ALL APPLICABLE REQUIREMENTS OF SECTION 605.11.1 THROUGH 605.11.4 OF THE 2012 EDITION OF THE INTERNATIONAL FIRE CODE, THE INTERNATIONAL BUILDING CODE AND NFPA 70. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08296
Permit Description: E - INSTALL ROOFTOP SOLAR SYSTEM
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2019 | TEP CLEARANCE - AM | DMUNIZ | Approved | CODE RECN/DGL |
| 12/18/2019 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Inspection for Line side tap Verbal Clearance sent to TEP @1:10PM (RECN/DGL). |
| 12/20/2019 | TEP CLEARANCE - PM | MRAMBER | Approved | CODE DGL/DGC |
| 12/20/2019 | ELECTRIC - FINAL | MRAMBER | Approved | DGL/DGC OK the clear. Permit OK to close. |
| 12/20/2019 | BUILDING - FINAL | MRAMBER | Approved | DGL/DGC OK the clear. Permit OK to close. |