Permit Details

Status:
L of c
Type:
COMMERCIAL NEW
Address NEW:
2121 N CRAYCROFT RD 8
Apply Date:
11/08/2019
Applicant:
C THOMAS DODD
Description:
E - NEW SHELL
Contractors:
  • RIO WEST DEVELOPMENT AND CONSTR *C*

Permit Reviews

Permit Number - T19CM08261
Permit Status: L of c
Permit Description: E - NEW SHELL
Start Date Submittal Complete Date Status  
01/23/2020 RESUB - SITE/GRADING ALL 02/18/2020 COMPLETED Review Details
02/18/2020 RESUBMITTAL 02/18/2020 COMPLETED Review Details
02/25/2020 REVISION - - 1ST 02/25/2020 COMPLETED Review Details
11/08/2019 PLANS OK TO SUBMIT - COMM 12/04/2019 COMPLETED Review Details
12/04/2019 COMMERCIAL - NEW 01/23/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM08261
Permit Status: L of c
Permit Description: E - NEW SHELL
Total Outstanding Activity Conditions - 1
Date Name
11/08/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T19CM08261
Permit Description: E - NEW SHELL
Total Completed Inspections - 23
Date Description Inspector Results Comments
02/20/2020 TEP CLEARANCE - PM ESTEVENS Approved CODE TMPP
02/20/2020 ELECTRIC - CONSTRUCTION POWER ESTEVENS Approved The TEP clearance code is TMPP
02/26/2020 PLUMBING - ROUGH, SOIL RCHANDLER Approved
03/03/2020 BUILDING PRE-SLAB RCHANDLER Approved
05/21/2020 PLUMBING - ROOF DRAINS DMUNIZ Approved Approved, Primary and secondary overflow drains Tested.
06/04/2020 FRAMING WGALLAGHER Approved
08/11/2020 REINFORCED MASONRY PRE-GROUT WGALLAGHER Approved Approved
10/27/2020 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved Ap
10/27/2020 STEM WALL/RETAINING WALL DQUINN Approved Ap
10/27/2020 EXT METAL CLIPS/EXT SHEATHING DQUINN Approved Ap
10/27/2020 BUILDING ABOVE CEILING DQUINN Approved Ap
10/27/2020 STUCCO MESH DQUINN Approved Ap
10/27/2020 U VALUE FOR WINDOW DQUINN Approved Ap
10/27/2020 FIREWALL/FIREBARRIER/FIRESTOP DQUINN Approved Ap
10/27/2020 ELECTRIC - UFER DQUINN Approved Ap
11/04/2020 FIRE - FINAL wmotto Approved
11/04/2020 FIRE - ALARM FINAL wmotto Approved
11/04/2020 FIRE SPKLR - FINAL wmotto Approved
11/10/2020 PLUMBING - FINAL CTREVIL Approved
11/10/2020 CERTIFICATE OF OCCUPANCY CTREVIL Approved
11/10/2020 BUILDING - FINAL CTREVIL Approved
11/10/2020 BUILDING - PROGRESS CTREVIL Approved
11/10/2020 ENGINEERING - FINAL CTREVIL Approved

Documents

File Name Document Type  
L OF C 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
L OF C.PDF DOCUMENTS VIEW