Permit: T19CM08261
Permit Details
Status:
L of c
Type:
COMMERCIAL NEW
Address:
2121 N CRAYCROFT RD 8
Address NEW:
2121 N CRAYCROFT RD 8
Apply Date:
11/08/2019
Applicant:
C THOMAS DODD
Description:
E - NEW SHELL
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T19CM08261
Permit Status: L of c
Permit Description: E - NEW SHELL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2020 | RESUB - SITE/GRADING ALL | 02/18/2020 | COMPLETED |
| 02/18/2020 | RESUBMITTAL | 02/18/2020 | COMPLETED |
| 02/25/2020 | REVISION - - 1ST | 02/25/2020 | COMPLETED |
| 11/08/2019 | PLANS OK TO SUBMIT - COMM | 12/04/2019 | COMPLETED |
| 12/04/2019 | COMMERCIAL - NEW | 01/23/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08261
Permit Status: L of c
Permit Description: E - NEW SHELL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/08/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM08261
Permit Description: E - NEW SHELL
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE TMPP |
| 02/20/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is TMPP |
| 02/26/2020 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 03/03/2020 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 05/21/2020 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Approved, Primary and secondary overflow drains Tested. |
| 06/04/2020 | FRAMING | WGALLAGHER | Approved | |
| 08/11/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Approved |
| 10/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 10/27/2020 | STEM WALL/RETAINING WALL | DQUINN | Approved | Ap |
| 10/27/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap |
| 10/27/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 10/27/2020 | STUCCO MESH | DQUINN | Approved | Ap |
| 10/27/2020 | U VALUE FOR WINDOW | DQUINN | Approved | Ap |
| 10/27/2020 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | Ap |
| 10/27/2020 | ELECTRIC - UFER | DQUINN | Approved | Ap |
| 11/04/2020 | FIRE - FINAL | wmotto | Approved | |
| 11/04/2020 | FIRE - ALARM FINAL | wmotto | Approved | |
| 11/04/2020 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 11/10/2020 | PLUMBING - FINAL | CTREVIL | Approved | |
| 11/10/2020 | CERTIFICATE OF OCCUPANCY | CTREVIL | Approved | |
| 11/10/2020 | BUILDING - FINAL | CTREVIL | Approved | |
| 11/10/2020 | BUILDING - PROGRESS | CTREVIL | Approved | |
| 11/10/2020 | ENGINEERING - FINAL | CTREVIL | Approved |