Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
11/05/2019
Applicant:
Albert LeCocq
Description:
BEDROOM AND BATH ADDITION for unit #2

Permit Reviews

Permit Number - T19CM08172
Permit Status: Expired
Permit Description: BEDROOM AND BATH ADDITION for unit #2
Start Date Submittal Complete Date Status  
11/05/2019 RESUBMITTAL 11/29/2019 ACTIVE Review Details
11/05/2019 RESIDENTIAL - BLDG/ZONING-WALKTHRU 11/05/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM08172
Permit Status: Expired
Permit Description: BEDROOM AND BATH ADDITION for unit #2
Total Outstanding Activity Conditions - 1
Date Name
11/05/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T19CM08172
Permite Description: BEDROOM AND BATH ADDITION for unit #2
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/07/2022 RSBU - Building Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T19CM08172
Permit Description: BEDROOM AND BATH ADDITION for unit #2
Total Completed Inspections - 14
Date Description Inspector Results Comments
03/11/2020 COT - RSPL - Rough Soil Passed {Activity date: 03/11/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} ; {Activity date: 03/09/2020; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Address to be posted on building. DWV has back pitch. Gas line to be relocated so as not to run under slab. Waterline unions and valves to be removed from under slab.?

}
03/19/2020 COT - RSBU - Preslab Passed {Activity date: 03/19/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by SFLORES2 - RVI}
03/19/2020 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/19/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by SFLORES2 - RVI}
04/09/2020 COT - RSBU - Roof Nailing Passed {Activity date: 04/09/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
04/09/2020 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 04/09/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/12/2020 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 05/12/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - RVI}
05/12/2020 COT - LCBU - Framing Passed {Activity date: 05/12/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - RVI}
05/12/2020 RSME - Mechanical Progress Passed {Activity date: 05/12/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - RVI}
08/10/2020 COT - RSME - Mechanical Final Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved. Southwest gas clearance is required.}
08/10/2020 COT - RSEL - Outdoor Lighting Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved. Southwest gas clearance is required.}
08/10/2020 COT - RSPL - Plumbing Final Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved. Southwest gas clearance is required.}
08/10/2020 COT - BULD - SWG Clearance Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - CODE
}
08/10/2020 COT - RSPL - Gas Pressure Test Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved. Southwest gas clearance is required.}
08/10/2020 COT - RSEL - Electrical Final Passed {Activity date: 08/10/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved. Southwest gas clearance is required.}

Documents

File Name Document Type  
001_S1.TIF CONSTRPLANS VIEW
002_N1.TIF CONSTRPLANS VIEW
003_A1.TIF CONSTRPLANS VIEW
004_A2.TIF CONSTRPLANS VIEW
005_A3.TIF CONSTRPLANS VIEW
006_A4.TIF CONSTRPLANS VIEW
007_A5.TIF CONSTRPLANS VIEW
008_A6.TIF CONSTRPLANS VIEW
009_E1.TIF CONSTRPLANS VIEW
010_P1.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW