Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM08121
Permit Details
Apply Date:
11/04/2019
Applicant:
RICHMOND AMERICAN HOMES ** APA ***
Description:
SFR RICHT920 T19-M0085
Contractors:
- RICHMOND AMERICAN HOMES ** APA ***
Permit Reviews
Permit Number - T19CM08121
Permit Status: Final
Permit Description: SFR RICHT920 T19-M0085
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/04/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 11/04/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08121
Permit Status: Final
Permit Description: SFR RICHT920 T19-M0085
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/04/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08121
Permit Description: SFR RICHT920 T19-M0085
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/15/2019 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | (RVI) |
11/15/2019 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | (RVI) |
11/15/2019 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | (RVI) |
11/22/2019 | ELECTRIC - UFER | BSTEVENS | Approved | (RVI) |
11/22/2019 | BUILDING PRE-SLAB | BSTEVENS | Approved | (RVI) |
11/22/2019 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | (RVI) |
12/09/2019 | ROOF NAILING | DMUNIZ | Approved | |
12/09/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
01/14/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Clear TEP ECO |
01/14/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
01/14/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas |
01/14/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
01/14/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
01/14/2020 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
01/14/2020 | FRAMING | DMUNIZ | Approved | |
01/24/2020 | SHEET ROCK NAILING | BSTEVENS | Approved | RVI |
03/02/2020 | GAS CLEARANCE | BSTEVENS | Approved | |
03/02/2020 | MECHANICAL - FINAL | BSTEVENS | Approved | RVI |
03/02/2020 | PLUMBING - FINAL | BSTEVENS | Approved | RVI |
03/02/2020 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | RVI |
03/02/2020 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | RVI |
03/03/2020 | ELECTRIC - FINAL | BSTEVENS | Approved | rvi |
03/03/2020 | BUILDING - FINAL | BSTEVENS | Approved | rvi |