Permit: T19CM07920
Permit Details
Apply Date:
10/25/2019
Applicant:
C A DEVELOPMENT AND CONSTRUCTION L L C
Description:
NEW SFR
Contractors:
- C A DEVELOPMENT AND CONSTRUCTION L L C
Permit Reviews
Permit Number - T19CM07920
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/28/2020 | RESUB - SITE/GRADING ALL | 03/17/2020 | COMPLETED |
| 03/17/2020 | RESUBMITTAL | 03/31/2020 | COMPLETED |
| 07/09/2020 | REVISION - - 1ST | 07/09/2020 | COMPLETED |
| 08/14/2020 | REVISION - - 2ND | 02/24/2021 | COMPLETED |
| 08/15/2022 | REVISION - - 2ND | 08/15/2022 | COMPLETED |
| 10/25/2019 | PLANS OK TO SUBMIT - RES | 10/28/2019 | COMPLETED |
| 10/28/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 12/12/2019 | COMPLETED |
| 12/16/2019 | RESUBMITTAL | 01/28/2020 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07920
Permit Description: NEW SFR
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2020 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | partial 1- Water line from meter to grade clean out is okay to cover. |
| 07/08/2020 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | partial 1- Bldg Sewer is okay from the HCS connection to the grade clean out. |
| 07/28/2020 | ELECTRIC - UFER | TVALENCIA | Approved | approved |
| 08/13/2020 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | T19CM07920 |
| 08/21/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Approved. |
| 09/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Approved. Porch footings and slab. |
| 11/04/2020 | ROOF NAILING | DQUINN | Approved | |
| 11/04/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 12/04/2020 | ENGINEERING - FINAL | DROBERTS | Approved | MET WITH THE CONTRACTOR TO VERIFY WHAT WAS HAPPENING WITH THIS SITE. MOST OF THE WORK ON THIS SITE IS VERTICAL WORK FOR THE NEW HOME, ROUGH GRADING FOR THE SITE ITSELF. |
| 04/29/2021 | TEP CLEARANCE - PM | TGAUPS | Approved | CODE ECO |
| 04/29/2021 | ELECTRIC - CONSTRUCTION POWER | TGAUPS | Approved | |
| 05/14/2021 | GAS CLEARANCE | DQUINN | Approved | CODE |
| 05/14/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 05/19/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 05/19/2021 | FRAMING | DQUINN | Approved | |
| 06/08/2021 | SHEET ROCK NAILING | DQUINN | Approved | |
| 11/12/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 11/12/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 11/12/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 11/12/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap |
| 11/12/2021 | BUILDING - FINAL | DQUINN | Approved | pa All ok. Pa until David’s DP sign off, then Ap 1090 and close permit |
| 11/12/2021 | FIRE - FINAL | wmotto | Approved | |
| 11/12/2021 | FIRE SPKLR - FINAL | wmotto | Approved |