Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
10/24/2019
Applicant:
Description:
SFR PLAN400318 T18-M0074

Permit Reviews

Permit Number - T19CM07866
Permit Status: Expired
Permit Description: SFR PLAN400318 T18-M0074
Start Date Submittal Complete Date Status  
10/24/2019 RESIDENTIAL - BLDG/ZONING-WALKTHRU 10/24/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM07866
Permit Status: Expired
Permit Description: SFR PLAN400318 T18-M0074
Total Outstanding Activity Conditions - 2
Date Name
10/24/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/24/2019 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)

Completed Inspections

Permit Status: Expired
Permit Number: T19CM07866
Permit Description: SFR PLAN400318 T18-M0074
Total Completed Inspections - 22
Date Description Inspector Results Comments
12/10/2019 COT - RSPL - Yard Water Line Passed {Activity date: 12/10/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Contractor cancelled via phone call.

}
12/10/2019 COT - RSPL - Sewer Passed {Activity date: 12/10/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Contractor cancelled via phone call.

}
12/10/2019 COT - RSPL - Rough Soil Passed {Activity date: 12/10/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Contractor cancelled via phone call.

}
12/17/2019 COT - RSEL - Grounding/Bonding Passed {Activity date: 12/17/2019; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
12/17/2019 COT - RSBU - Preslab Passed {Activity date: 12/17/2019; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
12/17/2019 COT - RSEL - Electrical Underground Passed {Activity date: 12/17/2019; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
12/17/2019 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 12/17/2019; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
01/10/2020 COT - RSBU - Roof Nailing Passed {Activity date: 01/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
01/10/2020 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 01/10/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - }
02/14/2020 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - }
02/14/2020 COT - LCBU - Framing Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - }
02/14/2020 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - }
02/14/2020 COT - BULD - SWG Clearance Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - }
02/14/2020 RSME - Mechanical Progress Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - }
02/14/2020 COT - RSPL - Gas Pressure Test Passed {Activity date: 02/14/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - Clear Southwest Gas}
02/21/2020 COT - RSEL - Construction Power Passed {Activity date: 02/21/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Clear TEP ECO}
02/26/2020 COT - HCBU - Interior Shear Bracing Passed {Activity date: 02/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by SFLORES2 - }
05/13/2020 COT - RSME - Mechanical Final Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 RSBU - Building Final Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - RSEL - Outdoor Lighting Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } ; {Activity date: 02/21/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - CODE ECO}
05/13/2020 COT - RSPL - Plumbing Final Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }
05/13/2020 COT - RSEL - Electrical Final Passed {Activity date: 05/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - }

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW