Permit: T19CM07786
Permit Details
Apply Date:
10/22/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW HOTEL
Architects:
- FUENTEVILLA, MIGUEL RAUL
Permit Reviews
Permit Number - T19CM07786
Permit Status: C of o
Permit Description: NEW HOTEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2020 | POST 3RD PARTY REVIEW | 01/22/2020 | COMPLETED |
| 10/22/2019 | PLANS OK TO SUBMIT - COMM | 10/22/2019 | COMPLETED |
| 10/23/2019 | 3RD PARTY REVIEW - COMMERCIAL | 01/15/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07786
Permit Status: C of o
Permit Description: NEW HOTEL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/22/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07786
Permit Description: NEW HOTEL
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2020 | GAS CLEARANCE | ESTEVENS | Approved | |
| 02/18/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Southwest Gas clearance is required |
| 02/26/2020 | ROOF NAILING | TVALENCIA | Approved | |
| 02/26/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 03/11/2020 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | 1- MC cables and metal boxes are okay to cover in all walls only. |
| 03/12/2020 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
| 03/12/2020 | PLUMBING - ABOVE CEILING | TVALENCIA | Approved | |
| 03/12/2020 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 03/17/2020 | SHEET ROCK NAILING | DQUINN | Approved | |
| 03/17/2020 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 03/17/2020 | STUCCO MESH | DQUINN | Approved | |
| 03/17/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 03/17/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 06/15/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 06/15/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 06/23/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | approved |
| 06/23/2020 | NPPO - FINAL | BBENEDON | Approved | Approved |
| 06/23/2020 | SIGN - FINAL | BBENEDON | Approved | Approved |
| 06/23/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | Approved |
| 06/23/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved |
| 06/23/2020 | RIGHT OF WAY - FINAL | DR | Approved | ROW OK |
| 06/23/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 06/24/2020 | PLUMBING - MD GAS/PRECONST MTG | TVALENCIA | Approved | SEE 3090 |
| 06/24/2020 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | approved |
| 06/24/2020 | PLUMBING - GAS PRESS TEST FNL | TVALENCIA | Approved | approved |
| 06/24/2020 | PLUMBING - ROOF DRAINS | TVALENCIA | Approved | approved |
| 06/24/2020 | PLUMBING - PRE SLAB | TVALENCIA | Approved | approved |
| 06/24/2020 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | approved |
| 06/24/2020 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | approved |
| 06/24/2020 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | approved |
| 06/24/2020 | ELECTRIC - CABLE DROP | TVALENCIA | Approved | approved |
| 06/24/2020 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | approved |
| 06/24/2020 | ELECTRIC - UFER | TVALENCIA | Approved | approved |
| 06/24/2020 | FRAMING | TVALENCIA | Approved | approved |
| 06/24/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | approved |
| 06/24/2020 | PLUMBING - FINAL | TVALENCIA | Approved | approved |
| 08/18/2020 | BUILDING - FINAL | JG3 | Approved |