Permit: T19CM07582
Permit Details
Apply Date:
10/15/2019
Applicant:
Description:
SFR T39919 T19-M0022
Permit Reviews
Permit Number - T19CM07582
Permit Status: Expired
Permit Description: SFR T39919 T19-M0022
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/15/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 10/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07582
Permit Status: Expired
Permit Description: SFR T39919 T19-M0022
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/15/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T19CM07582
Permit Status: Expired
Permit Description: SFR T39919 T19-M0022
Date | Description | Comments |
---|---|---|
10/15/2019 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
10/15/2019 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM07582
Permit Description: SFR T39919 T19-M0022
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/24/2019 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Note: Remove any large boulders and backfill with clean fill. } |
|
10/24/2019 | COT - RSPL - Sewer | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Note: Remove any large boulders and backfill with clean fill. } |
|
10/24/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Note: Remove any large boulders and backfill with clean fill. } |
|
10/30/2019 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/30/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } | |
10/30/2019 | COT - RSBU - Preslab | Passed | {Activity date: 10/30/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } | |
10/30/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/30/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } | |
12/02/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 12/02/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made ok to proceed. } ; {Activity date: 11/27/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } |
|
12/02/2019 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 12/02/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made ok to proceed. } ; {Activity date: 11/27/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } |
|
01/15/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | COT - LCBU - Framing | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - CODE ECO} | |
01/15/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Clear TEP ECO} ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
01/15/2020 | RSME - Mechanical Progress | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/15/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 01/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - CLEAR SOUTHWEST GAS} ; {Activity date: 01/13/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Rescheduled Via phone call. } |
|
01/24/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 01/24/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - RVI} | |
03/12/2020 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/12/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - RVI} | |
03/12/2020 | RSBU - Building Final | Passed | {Activity date: 03/12/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - RVI} | |
03/12/2020 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/12/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - RVI} | |
03/12/2020 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/12/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - RVI} | |
03/12/2020 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/12/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - RVI} |