Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM07397
Permit Details
Apply Date:
10/09/2019
Applicant:
MATT WILLIAMS
Description:
NEW DRIVE THRU/WALK UP COFFEE SHOP
Architects:
- A23 STUDIOS
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM07397
Permit Status: C of o
Permit Description: NEW DRIVE THRU/WALK UP COFFEE SHOP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/13/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 03/05/2020 | COMPLETED |
10/09/2019 | PLANS OK TO SUBMIT - COMM | 10/09/2019 | COMPLETED |
10/09/2019 | 3RD PARTY REVIEW - COMMERCIAL | 11/14/2019 | COMPLETED |
11/14/2019 | POST 3RD PARTY REVIEW | 12/04/2019 | COMPLETED |
12/04/2019 | POST 3RD PARTY REVIEW | 01/09/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07397
Permit Status: C of o
Permit Description: NEW DRIVE THRU/WALK UP COFFEE SHOP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/09/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07397
Permit Description: NEW DRIVE THRU/WALK UP COFFEE SHOP
Total Completed Inspections - 51
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/03/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
12/03/2019 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
01/10/2020 | ELECTRIC - UFER | ESTEVENS | Approved | |
01/16/2020 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
01/27/2020 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
01/27/2020 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
02/14/2020 | PLUMBING - PRE SLAB | RCHANDLER | Approved | |
02/14/2020 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
02/19/2020 | SEPTIC - SYSTEM | ESTEVENS | Approved | |
02/19/2020 | SITE - SEWER | ESTEVENS | Approved | |
02/25/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
02/25/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
02/28/2020 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
03/09/2020 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | |
03/09/2020 | ROOF NAILING | MRAMBER | Approved | |
03/12/2020 | MECHANICAL - HOOD SYSTEMS | MRAMBER | Approved | |
03/12/2020 | MECHANICAL - HOODS | MRAMBER | Approved | |
03/12/2020 | PLUMBING - MEDICAL GAS/FINAL | MRAMBER | Approved | |
03/12/2020 | PLUMBING - MD GAS/PRECONST MTG | MRAMBER | Approved | |
03/12/2020 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
03/12/2020 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
03/12/2020 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
03/12/2020 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
03/12/2020 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | |
03/12/2020 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
03/12/2020 | FRAMING | MRAMBER | Approved | |
03/25/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
03/25/2020 | ELECTRIC - CABLE DROP | ESTEVENS | Approved | The TEP clearance code is ECO. |
04/06/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
04/06/2020 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
04/06/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
05/11/2020 | FIRE - FINAL | MRoss | Approved | |
05/11/2020 | NPPO - FINAL | BBENEDON | Approved | Will complete inspections under development package permit. |
05/11/2020 | SIGN - FINAL | BBENEDON | Approved | Will complete inspections under development package permit. |
05/11/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | Will complete inspections under development package permit. |
05/11/2020 | MECHANICAL - PROGRESS | TTREMBULAK | Approved | RVI |
05/11/2020 | MECHANICAL - UNDERGROUND | TTREMBULAK | Approved | RVI |
05/11/2020 | PLUMBING - PROGRESS | TTREMBULAK | Approved | RVI |
05/11/2020 | PLUMBING - BACK WATER VALVE | TTREMBULAK | Approved | RVI |
05/11/2020 | PLUMBING - MEDICAL GAS/TEST | TTREMBULAK | Approved | RVI |
05/11/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | RVI |
05/11/2020 | ELECTRIC - OUTDOOR LIGHTING | TTREMBULAK | Approved | RVI |
05/11/2020 | BUILDING - FINAL | TTREMBULAK | Approved | RVI |
05/11/2020 | SHEET ROCK NAILING | TTREMBULAK | Approved | RVI |
05/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | RVI |
05/13/2020 | PLUMBING - GAS RECONNECT | TTREMBULAK | Approved | RVI |
05/13/2020 | PLUMBING - GAS PRESS TEST FNL | TTREMBULAK | Approved | RVI |
05/13/2020 | OUTDOOR LIGHTING FINAL | TTREMBULAK | Approved | RVI |
05/14/2020 | HEALTH DEPT - FINAL 724-7908 | RSHERRY | Approved | HEALTH DEPT INSPECTION 5/12/20 BY PRISCILLA URBINA |
05/15/2020 | ENGINEERING - FINAL | BBENEDON | Approved | |
05/18/2020 | RIGHT OF WAY - FINAL | DR | Approved | Out of Spec Sidewalk removed and replaced. |