Permit: T19CM07279
Permit Details
Apply Date:
10/04/2019
Applicant:
DONALD LIVINGSTONE
Description:
SFR - MODEL 1686 T19-M0088
Contractors:
- DELAOSSA INVESTMENTS LLC
Permit Reviews
Permit Number - T19CM07279
Permit Status: C of o
Permit Description: SFR - MODEL 1686 T19-M0088
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/04/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/07/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07279
Permit Status: C of o
Permit Description: SFR - MODEL 1686 T19-M0088
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/04/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07279
Permit Description: SFR - MODEL 1686 T19-M0088
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2019 | ROOF NAILING | TW | Approved | ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION |
| 11/06/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 11/06/2019 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 11/06/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 11/19/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 11/19/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 12/13/2019 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 12/13/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric eco |
| 12/13/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 02/03/2020 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
| 02/03/2020 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 02/03/2020 | RESIDENTIAL INTERMEDIATE | TVALENCIA | Approved | |
| 02/03/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 04/07/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 04/07/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 04/07/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | |
| 04/07/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 04/07/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 04/07/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
| 04/07/2020 | ELECTRIC - UFER | DMUNIZ | Approved | |
| 04/07/2020 | FRAMING | DMUNIZ | Approved |