Permit: T19CM07190
Permit Details
Apply Date:
10/02/2019
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Description:
SFR PEPP1175 T19-M0090
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T19CM07190
Permit Status: Final
Permit Description: SFR PEPP1175 T19-M0090
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/02/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/23/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07190
Permit Status: Final
Permit Description: SFR PEPP1175 T19-M0090
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM07190
Permit Description: SFR PEPP1175 T19-M0090
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 11/13/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 11/13/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 11/25/2019 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | |
| 11/25/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
| 11/25/2019 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 11/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
| 12/17/2019 | TEP CLEARANCE - AM | MRAMBER | Approved | CODE ECO |
| 12/17/2019 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | ECO OK to clear. |
| 12/17/2019 | ROOF NAILING | MRAMBER | Approved | |
| 12/17/2019 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | |
| 01/29/2020 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 01/29/2020 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 01/30/2020 | RESIDENTIAL INTERMEDIATE | RCHADLER | Approved | |
| 01/30/2020 | FRAMING | RCHADLER | Approved | |
| 02/20/2020 | SHEET ROCK NAILING | WGALLAG1 | Approved | |
| 04/22/2020 | GAS CLEARANCE | WGALLAGHER | Approved | CODE |
| 04/22/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | ok for clearance SWG |
| 04/23/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 04/23/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 04/23/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 04/23/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 04/23/2020 | BUILDING - FINAL | DMUNIZ | Approved |