Permit: T19CM07082
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
1173 S COYOTE SUMMIT PL
Address NEW:
1173 S COYOTE SUMMIT PL
Apply Date:
09/27/2019
Applicant:
LENNAR ARIZONA CONSTRUCTION INC **APA**
Description:
NEW SFR PLAN456919 T19-M0095
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC **APA**
Outstanding Activity Conditions
Permit Number - T19CM07082
Permit Status: Final
Permit Description: NEW SFR PLAN456919 T19-M0095
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/27/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM07082
Permit Description: NEW SFR PLAN456919 T19-M0095
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/21/2019 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
| 10/21/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 10/21/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 11/01/2019 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
| 11/01/2019 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 11/01/2019 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 11/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
| 11/18/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 11/18/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 11/27/2019 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 11/27/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric eco |
| 12/27/2019 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | |
| 12/27/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 12/27/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 12/27/2019 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | |
| 12/27/2019 | FRAMING | ESTEVENS | Approved | |
| 01/07/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | |
| 03/16/2020 | GAS CLEARANCE | ESTEVENS | Approved | |
| 03/16/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | Southwest gas clearance is required for a gas meter. |
| 03/16/2020 | PLUMBING - FINAL | ESTEVENS | Approved | Southwest gas clearance is required for a gas meter. |
| 03/16/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | Southwest gas clearance is required for a gas meter. |
| 03/16/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Southwest gas clearance is required for a gas meter. |
| 03/16/2020 | BUILDING - FINAL | ESTEVENS | Approved | Southwest gas clearance is required for a gas meter. |