Permit: T19CM06808
Permit Details
Status:
L of c
Type:
COMMERCIAL OTHER
Address:
6325 N VALLEY VIEW RD
Address NEW:
6325 N VALLEY VIEW RD
Apply Date:
09/18/2019
Applicant:
SMYTH STEEL MANUFACTURING INC
Description:
E - REHAB EXISTING STORGE TANK/PIPING, UPGRADE ELECTRICAL SCADA SYSTEM
Contractors:
- SMYTH STEEL MANUFACTURING INC
Permit Reviews
Permit Number - T19CM06808
Permit Status: L of c
Permit Description: E - REHAB EXISTING STORGE TANK/PIPING, UPGRADE ELECTRICAL SCADA SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/18/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 11/08/2019 | COMPLETED |
| 11/08/2019 | RESUBMITTAL | 11/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06808
Permit Status: L of c
Permit Description: E - REHAB EXISTING STORGE TANK/PIPING, UPGRADE ELECTRICAL SCADA SYSTEM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/18/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM06808
Permit Description: E - REHAB EXISTING STORGE TANK/PIPING, UPGRADE ELECTRICAL SCADA SYSTEM
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2020 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 01/28/2020 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 02/11/2020 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 02/11/2020 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 04/29/2020 | TEP CLEARANCE - AM | ESTEVENS | Approved | CODE ECO |
| 04/29/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
| 09/24/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 09/24/2020 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | na |
| 09/24/2020 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | 2090 |
| 09/24/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 09/24/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 09/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 09/29/2020 | BUILDING - FINAL | BSTEVENS | Approved |