Permit: T19CM06729
Permit Details
Apply Date:
09/16/2019
Applicant:
N/A
Description:
SFR DEMO SFR -T19BU00442
Contractors:
- SILVA DIVERSIFIED CONSTRUCTION CO LLC
Permit Reviews
Permit Number - T19CM06729
Permit Status: Final
Permit Description: SFR
DEMO SFR -T19BU00442
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/16/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 09/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06729
Permit Status: Final
Permit Description: SFR
DEMO SFR -T19BU00442
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/16/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM06729
Permit Description: SFR
DEMO SFR -T19BU00442
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2019 | PLUMBING - FINAL | rmccoy | Approved | Deferred submittal for 1] Manual J , 2] Truss Calculations |
| 10/03/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 10/03/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | Note: Instructed person on site to have footings at front of garage dug a little deeper to meet Code and install hold downs per approved plans. |
| 10/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 10/15/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 10/17/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 10/22/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 10/22/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
| 10/25/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 10/25/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 10/25/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 10/25/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 10/25/2019 | STUCCO MESH | DQUINN | Approved | |
| 10/28/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | APPROVED PER 3090 APPROVAL |
| 10/28/2019 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | APPROVED PER 1090 APPROVAL |
| 10/28/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | APPROVED PER 1090 APPROVAL |
| 10/28/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
| 10/28/2019 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | |
| 10/28/2019 | FRAMING | ESTEVENS | Approved | |
| 10/28/2019 | MECHANICAL - FINAL | ESTEVENS | Approved | APPROVED PER 1090 APPROVAL |