Permit: T19CM06576
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
3030 E SAM HUGHES CT
Address NEW:
3030 E SAM HUGHES CT
Apply Date:
09/10/2019
Applicant:
A F STERLING HOME BUILDERS LTD
Description:
SFR AFSH328719 T19-M0065
Contractors:
- A F STERLING HOME BUILDERS LTD
Permit Reviews
Permit Number - T19CM06576
Permit Status: Final
Permit Description: SFR AFSH328719 T19-M0065
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/10/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 09/10/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06576
Permit Status: Final
Permit Description: SFR AFSH328719 T19-M0065
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/10/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM06576
Permit Description: SFR AFSH328719 T19-M0065
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/03/2019 | PLUMBING - SEWER HCS CONNECT | JCLAXTON | Approved | Ok to proceed |
| 12/03/2019 | PLUMBING - YARD WTR LINE/TEST | JCLAXTON | Approved | Ok to proceed |
| 12/03/2019 | PLUMBING - ROUGH, SOIL | JCLAXTON | Approved | Ok to proceed |
| 12/09/2019 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 12/11/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 12/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 01/16/2020 | ROOF NAILING | DQUINN | Approved | |
| 01/16/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 04/08/2020 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 04/08/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 04/08/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 04/08/2020 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
| 04/08/2020 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 04/08/2020 | FRAMING | DQUINN | Approved | |
| 05/11/2020 | SHEET ROCK NAILING | TVALENCIA | Approved | |
| 08/11/2020 | BUILDING - FINAL | BSTEVENS | Approved | |
| 08/11/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
| 08/11/2020 | BUILDING - FINAL | ESTEVENS | Approved | Partial. Pending certifications. |
| 08/11/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | All four are approved. |
| 08/11/2020 | PLUMBING - FINAL | ESTEVENS | Approved | All four are approved. |
| 08/11/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | All four are approved. |
| 08/11/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | All four are approved. |
| 08/11/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | N/A. |
| 08/11/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | N/A. |
| 08/11/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Southwest gas clearance is required. |