Permit: T19CM06409
Permit Details
Apply Date:
09/04/2019
Applicant:
N/A
Description:
NEW RESTAURANT
Architects:
- MEYER WILLIAM (CHUCK)
Contractors:
- PATE CONTRACTORS LLC
Permit Reviews
Permit Number - T19CM06409
Permit Status: C of o
Permit Description: NEW RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2020 | REVISION - - 2ND | 01/30/2020 | COMPLETED |
03/10/2020 | REVISION - - 3RD | 03/11/2020 | COMPLETED |
09/04/2019 | COMMERCIAL - NEW | 09/05/2019 | COMPLETED |
09/05/2019 | COMMERCIAL - NEW | 10/31/2019 | COMPLETED |
10/31/2019 | RESUBMITTAL | 12/12/2019 | COMPLETED |
12/12/2019 | REVISION - - 1ST | 12/12/2019 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM06409
Permit Description: NEW RESTAURANT
Total Completed Inspections - 45
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/25/2019 | NPPO - FINAL | RLEDONNE | Approved | Met with GC on site went over Approved plans. |
11/27/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
12/03/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | 3-2" Electrical Conduits under slab from Interior panels to location of future Exterior Disconnects ok to backfill. 2-1" Conduits under slab for future Light poles ok. |
12/09/2019 | ELECTRIC - UFER | DMUNIZ | Approved | 3-3/0 Cu EGC connections to rebar for Service entrance, water, & Gas ok. |
12/10/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
12/10/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
01/09/2020 | ROOF NAILING | WGALLAG1 | Approved | |
01/09/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAG1 | Approved | |
01/22/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Electrical in walls. |
01/22/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | |
01/22/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Mechanical In Hard lid areas inspected. |
01/22/2020 | FRAMING | DMUNIZ | Approved | Interior Framing. |
01/22/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Roof drains, and DWV in walls. |
02/11/2020 | STUCCO MESH | DMUNIZ | Approved | |
02/19/2020 | SHEET ROCK NAILING | DMUNIZ | Approved | |
02/19/2020 | PLUMBING - PRE SLAB | DMUNIZ | Approved | |
02/19/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | |
02/19/2020 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | |
02/19/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
02/19/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Clear TEP ECO. |
02/27/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
02/27/2020 | PLUMBING - BACK WATER VALVE | DMUNIZ | Approved | |
02/27/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
03/17/2020 | GAS CLEARANCE | DMUNIZ | Approved | |
03/17/2020 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Clear Southwest Gas |
03/25/2020 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
03/26/2020 | ELECTRIC - PROGRESS | WGALLAGHER | Approved | |
03/26/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | |
03/26/2020 | MECHANICAL - ABOVE CEILING | WGALLAGHER | Approved | |
03/26/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | |
03/26/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | |
03/26/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
03/31/2020 | SIGN - FINAL | DROBERTS | Approved | |
03/31/2020 | FIRE - FINAL | jvincent | Approved | Final inspection approved via phone video due to COVID-19 |
03/31/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | |
03/31/2020 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
03/31/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | |
03/31/2020 | ELECTRIC - ABOVE CEILING | WGALLAGHER | Approved | |
03/31/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | |
03/31/2020 | FIRE - FINAL | jvincent | Approved | Items outstanding: 1) Pay outstanding fees on places of assembly permit. 2) Post OL sign. |
03/31/2020 | FIRE - KITCHEN EXH HOOD FINAL | jvincent | Approved | |
04/02/2020 | LANDSCAPE - FINAL | DROBERTS | Approved | |
04/02/2020 | RIGHT OF WAY - FINAL | DR | Approved | No work in ROW. |
04/06/2020 | ENGINEERING - FINAL | DROBERTS | Approved | |
04/08/2020 | BUILDING - FINAL | WGALLAGHER | Approved | Inspection not required see previous inspection ok for TCO |