Permit: T19CM06331
Permit Details
Apply Date:
08/30/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW COMMERCIAL SHELL ONLY
Contractors:
- M A S DEVELOPMENT INC *APA*
Permit Reviews
Permit Number - T19CM06331
Permit Status: Final
Permit Description: NEW COMMERCIAL SHELL ONLY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/30/2019 | PLANS OK TO SUBMIT - COMM | 08/30/2019 | COMPLETED |
| 09/04/2019 | COMMERCIAL - NEW | 10/25/2019 | COMPLETED |
| 10/25/2019 | RESUBMITTAL | 11/04/2019 | COMPLETED |
| 11/04/2019 | RESUBMITTAL | 11/14/2019 | COMPLETED |
| 11/14/2019 | RESUBMITTAL | 11/15/2019 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T19CM06331
Permit Status: Final
Permit Description: NEW COMMERCIAL SHELL ONLY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/30/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM06331
Permit Description: NEW COMMERCIAL SHELL ONLY
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/25/2019 | ROOF NAILING | ENEWCOMB | Approved | Roof joist calculations and drawings must be reviewed and approved by the City of Tucson before the P2I Action can be approved. |
| 11/21/2019 | PLUMBING - INTERMEDIATE | CLAYTON | Approved | sewer fees to be paid prior to intermediate inspections |
| 11/21/2019 | MECHANICAL - INTERMEDIATE | CLAYTON | Approved | sewer fees to be paid prior to intermediate inspections |
| 11/21/2019 | ELECTRIC - INTERMEDIATE | CLAYTON | Approved | sewer fees to be paid prior to intermediate inspections |
| 11/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | OK TO POUR ALL FOOTINGS |
| 12/17/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 12/18/2019 | BUILDING PRE-SLAB | WGALLAG1 | Approved | |
| 12/24/2019 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | 1- First lift is okay for grout. |
| 03/23/2020 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
| 06/17/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
| 06/22/2020 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | approved |
| 06/25/2020 | PLUMBING - BACK WATER VALVE | DMUNIZ | Approved | Approved |
| 06/25/2020 | FRAMING | DMUNIZ | Approved | Approved |
| 06/30/2020 | TEP CLEARANCE - AM | TVALENCIA | Approved | CODE ECO/STE 151 & OWNERS METER |
| 06/30/2020 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | CODE ECO |
| 06/30/2020 | SITE - SEWER | TVALENCIA | Approved | approved |
| 06/30/2020 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | NA |
| 06/30/2020 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | approved |
| 06/30/2020 | ELECTRIC - TEMPORARY SERVICE | TVALENCIA | Approved | approved Clear electric ECO Suite 151 & Owners Meter. |
| 06/30/2020 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | approved |
| 06/30/2020 | ELECTRIC - UFER | TVALENCIA | Approved | approved |
| 06/30/2020 | BUILDING - PROGRESS | TVALENCIA | Approved | approved |
| 06/30/2020 | U VALUE FOR WINDOW | TVALENCIA | Approved | approved |
| 07/13/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | NA 1- Item not needed. |
| 07/13/2020 | BUILDING ABOVE CEILING | TVALENCIA | Approved | approved |
| 07/20/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 07/21/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | approved |
| 07/21/2020 | PLUMBING - FINAL | TVALENCIA | Approved | approved |
| 07/21/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | approved |
| 07/31/2020 | BUILDING - FINAL | DMUNIZ | Approved | Approved |
| 07/31/2020 | ENGINEERING - FINAL | BBENEDON | Approved | . Approved |