Permit: T19CM06263
Permit Details
Apply Date:
08/28/2019
Applicant:
N/A
Description:
NEW DUPLEX
Contractors:
- ODAMA CONSTRUCTION AND ROOFING CO
Permit Reviews
Permit Number - T19CM06263
Permit Status: Final
Permit Description: NEW DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/28/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/29/2019 | COMPLETED |
| 08/29/2019 | RESIDENTIAL - BLDG/WWM | 09/13/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06263
Permit Status: Final
Permit Description: NEW DUPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/28/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM06263
Permit Description: NEW DUPLEX
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2019 | ELECTRIC - UFER | TVALENCIA | Approved | 1- Ufer ground conductor provided |
| 10/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 11/01/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 11/07/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 11/20/2019 | RESIDENTIAL INTERMEDIATE | JCLAXTON | Approved | Mistake hit wrong numbers |
| 12/03/2019 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
| 12/09/2019 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | |
| 12/17/2019 | FRAMING | TVALENCIA | Approved | 1- Item called in error |
| 12/17/2019 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 12/17/2019 | ROOF NAILING | TVALENCIA | Approved | |
| 12/24/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 01/10/2020 | GAS CLEARANCE | DQUINN | Approved | |
| 01/10/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
| 01/10/2020 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
| 01/10/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 01/10/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 01/30/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Electric power is on, no clearance to TEP needed. |
| 04/27/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | |
| 04/27/2020 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 04/27/2020 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 04/27/2020 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 04/27/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 04/27/2020 | BUILDING - FINAL | TVALENCIA | Approved |