Permit Details

Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Apply Date:
08/27/2019
Applicant:
Joseph Maher
Description:
NEW 2 STORY ADDITION/REMODEL

Permit Reviews

Permit Number - T19CM06183
Permit Status: Inspections complete
Permit Description: NEW 2 STORY ADDITION/REMODEL
Start Date Submittal Complete Date Status  
08/27/2019 RESIDENTIAL - BLDG/ZONING-WALKTHRU 10/16/2020 COMPLETED Review Details
10/16/2020 3RD PARTY REVIEW - RESIDENTIAL 11/03/2020 COMPLETED Review Details
11/04/2020 RESUBMITTAL 11/24/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM06183
Permit Status: Inspections complete
Permit Description: NEW 2 STORY ADDITION/REMODEL
Total Outstanding Activity Conditions - 1
Date Name
08/27/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: T19CM06183
Permite Description: NEW 2 STORY ADDITION/REMODEL
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
10/01/2021 COT - RSBU - Stem Wall/Retaining Wall N/A Canceled {Activity date: 10/01/2021; Status: Not Applicable; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not a required inspection}
12/21/2021 COT - RSBU - Exterior Clips/Sheathing N/A Canceled {Activity date: 12/21/2021; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by NGARCIA3 - na
Note: special inspection for apoxy not needed, as wall framing was changed from wood to block.}
02/08/2022 COT - RSEL - Grounding/Bonding N/A Canceled {Activity date: 02/08/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - N/A}
02/08/2022 COT - RSEL - Construction Power N/A Canceled {Activity date: 02/08/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - N/A}
10/27/2022 RSBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: T19CM06183
Permit Description: NEW 2 STORY ADDITION/REMODEL
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/23/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 02/23/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VLEON1 - CODE INCR}
02/23/2021 COT - RSEL - Service Upgrade Passed {Activity date: 02/23/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VLEON1 - APPROVED OK TO ENERGIZE NEW 400 AMP PANEL}
10/04/2021 COT - RSPL - Rough Soil Passed {Activity date: 10/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved
} ; {Activity date: 09/21/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - . Partial. Sewer line (4”) from new slab/house to main sewer connection. Ok to cover progress areas.}
10/04/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 10/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved
} ; {Activity date: 10/01/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval need dobies under rebar}
10/19/2021 COT - RSEL - Electrical Underground Passed {Activity date: 10/19/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
12/21/2021 COT - RSBU - Preslab Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 09/28/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Plumbing for garage slab; in place and properly wrapped.

}
12/21/2021 COT - RSBU - Sustainability Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
12/21/2021 COT - RSBU - Masonry Pregrout Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 11/10/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa
N, E, and S. Walls ok to grout to top out.} ; {Activity date: 11/09/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Canceled by homeowner} ; {Activity date: 10/19/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for 2nd lift ok to grout} ; {Activity date: 10/14/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. 1st lift, 0 to 4 feet.

}
12/21/2021 COT - HCBU - Interior Shear Bracing Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Note: special inspection for apoxy not needed, as wall framing was changed from wood to block.}
02/04/2022 COT - RSBU - Roof Nailing Passed {Activity date: 02/04/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
02/04/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 02/04/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
02/08/2022 COT - LCBU - Framing Passed {Activity date: 02/08/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Southwest gas clearance is required.}
02/08/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/08/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Southwest gas clearance is required.}
02/08/2022 COT - BULD - SWG Clearance Passed {Activity date: 02/08/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - CODE GAS} ; {Activity date: 03/02/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - CODE}
02/08/2022 RSEL - Electrical Progress Passed {Activity date: 02/08/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Southwest gas clearance is required.}
02/08/2022 RSME - Mechanical Progress Passed {Activity date: 02/08/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Southwest gas clearance is required.}
08/26/2022 COT - RSEL - Construction Power Passed {Activity date: 08/26/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved}
12/23/2022 COT - RSPL - Gas Pressure Test Passed
01/27/2023 COT - RSME - Mechanical Final Passed
06/27/2023 COT - RSPL - Plumbing Final Passed
06/27/2023 COT - RSEL - Electrical Final Passed
06/17/2024 RSBU - Building Final Passed