Permit: T19CM06136
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
5850 N 1ST AV BLDG #1
Address NEW:
5850 N 1ST AV BLDG #1
Apply Date:
08/26/2019
Applicant:
GILBER ALABADO, AIA - GLHN A/E
Description:
700 SQ FT ADDITION
Architects:
- HAGEDON, BRIAN GEORGE
Permit Reviews
Permit Number - T19CM06136
Permit Status: C of o
Permit Description: 700 SQ FT ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/26/2019 | PLANS OK TO SUBMIT - COMM | 08/26/2019 | COMPLETED |
| 08/26/2019 | COMMERCIAL - TI | 10/16/2019 | COMPLETED |
| 08/26/2020 | REVISION - - 1ST | 09/02/2020 | COMPLETED |
| 10/23/2019 | RESUBMITTAL - TI ALL | 11/27/2019 | COMPLETED |
| 11/27/2019 | RESUBMITTAL | 08/26/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06136
Permit Status: C of o
Permit Description: 700 SQ FT ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/26/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM06136
Permit Description: 700 SQ FT ADDITION
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/02/2019 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 06/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | approved |
| 07/08/2020 | BUILDING PRE-SLAB | BSTEVENS | Approved | AP |
| 08/07/2020 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Approved. 3rd lift top-out. |
| 09/24/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | pa Pa in case needed in lid area. Above ceiling nr. |
| 09/24/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap All in wall conduits ok. Ok to rock walls. |
| 09/24/2020 | FRAMING | DQUINN | Approved | Ap |
| 09/24/2020 | ROOF NAILING | DQUINN | Approved | Ap |
| 11/09/2020 | SHEET ROCK NAILING | DQUINN | Approved | |
| 11/12/2020 | ELECTRIC - FINAL | DQUINN | Approved | Light pole cage and ufer ok to pour. |
| 12/16/2020 | U VALUE FOR WINDOW | DQUINN | Approved | APPROVED |
| 12/16/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | APPROVED |
| 12/16/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | APPROVED |
| 12/16/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | APPROVED |
| 01/14/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | APPROVED |
| 01/14/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | APPROVED |
| 04/08/2021 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 04/08/2021 | MECHANICAL - PROGRESS | DQUINN | Approved | APPROVED WHEN ENG IS APPROVED, APPROVE 1090 |
| 07/06/2021 | BUILDING - FINAL | CTREVIL | Approved |