Permit: T19CM06128
Permit Details
Apply Date:
08/23/2019
Applicant:
VANCE GOODMAN
Description:
OFFICE
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM06128
Permit Status: C of o
Permit Description: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/23/2019 | PLANS OK TO SUBMIT - COMM | 09/03/2019 | COMPLETED |
| 09/03/2019 | COMMERCIAL - TI | 09/20/2019 | COMPLETED |
| 09/20/2019 | RESUBMITTAL | 09/24/2019 | COMPLETED |
| 09/24/2019 | RESUBMITTAL | 09/27/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06128
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/23/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM06128
Permit Description: OFFICE
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2019 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | |
| 10/01/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 10/01/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
| 10/01/2019 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
| 10/01/2019 | FRAMING | MRAMBER | Approved | |
| 11/04/2019 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
| 11/04/2019 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | |
| 11/04/2019 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
| 11/13/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 11/13/2019 | BUILDING - PROGRESS | MRAMBER | Approved | |
| 11/13/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | ADA Parking and on site access does not meet ICC. Owner has been made aware |
| 11/15/2019 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
| 11/15/2019 | FIRE - FINAL | gsereno1 | Approved | |
| 11/15/2019 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
| 11/15/2019 | FIRE - FINAL | gsereno1 | Approved | Missing an escucheons and a ceiling tile has to be re-cut so there is no gap. Water gong not functioning, shall repair. |
| 11/19/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
| 11/25/2019 | BUILDING - FINAL | MRAMBER | Approved | |
| 11/25/2019 | CERTIFICATE OF OCCUPANCY | MRAMBER | Approved | |
| 11/25/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |