Permit: T19CM06023
Permit Details
Apply Date:
08/22/2019
Applicant:
N/A
Description:
WAREHOUSE
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T19CM06023
Permit Status: C of o
Permit Description: WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/22/2019 | COMMERCIAL - TI | 09/05/2019 | COMPLETED |
09/05/2019 | RESUBMITTAL | 09/10/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06023
Permit Status: C of o
Permit Description: WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/22/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM06023
Permit Description: WAREHOUSE
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/04/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
10/15/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
10/15/2019 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
10/15/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/15/2019 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
10/15/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
10/31/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
10/31/2019 | FIRE - FINAL | CBASALDUA | Approved | |
10/31/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
10/31/2019 | NPPO - FINAL | BBENEDON | Approved | Note the IVR system was down and I was not able to retrieve the contractors phone number or provide the call requested. |
10/31/2019 | SIGN - FINAL | BBENEDON | Approved | Note the IVR system was down and I was not able to retrieve the contractors phone number or provide the call requested. |
10/31/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | Note the IVR system was down and I was not able to retrieve the contractors phone number or provide the call requested. |
10/31/2019 | ENGINEERING - FINAL | BBENEDON | Approved | Note the IVR system was down and I was not able to retrieve the contractors phone number or provide the call requested. |
10/31/2019 | PLUMBING - FINAL | DQUINN | Approved | Upon approval of all other entities, approve the above finals and close permit. |
10/31/2019 | RIGHT OF WAY - FINAL | DR | Approved | No COT ROW impact. |
11/05/2019 | ELECTRIC - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED. |
11/08/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | |
11/13/2019 | BUILDING - FINAL | DQUINN | Approved |