Permit: T19CM06001
Permit Details
Apply Date:
08/21/2019
Applicant:
SONORAN DESIGN GROUP, INC
Description:
DUPLX DPM2248 T19-M0079
Contractors:
- C G BACHELIER MASTERPIECES L L C
Permit Reviews
Permit Number - T19CM06001
Permit Status: Final
Permit Description: DUPLX DPM2248 T19-M0079
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/21/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/30/2019 | COMPLETED |
08/30/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06001
Permit Status: Final
Permit Description: DUPLX DPM2248 T19-M0079
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/21/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM06001
Permit Description: DUPLX DPM2248 T19-M0079
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/12/2019 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
09/12/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
09/12/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
09/17/2019 | ELECTRIC - UFER | DQUINN | Approved | |
09/17/2019 | BUILDING PRE-SLAB | DQUINN | Approved | |
09/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
10/04/2019 | FRAMING | DQUINN | Approved | |
10/04/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
10/18/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/18/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
10/18/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
01/07/2020 | TEP CLEARANCE - AM | ESTEVENS | Approved | Units A&B CODE ECO |
01/07/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. Units A&B. |
01/07/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | Approved by Dan Quinn on Oct 4, 2019. |
01/07/2020 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | Approved by Dan Quinn on Oct 4, 2019. |
01/07/2020 | ROOF NAILING | ESTEVENS | Approved | Approved by Dan Quinn on Oct 4, 2019. |
03/25/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
03/25/2020 | PLUMBING - FINAL | ESTEVENS | Approved | |
03/25/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | |
04/01/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | |
04/01/2020 | BUILDING - FINAL | ESTEVENS | Approved |