Permit: T19CM05885
Permit Details
Apply Date:
08/16/2019
Applicant:
N/A
Description:
SFR
Architects:
- DIANE KREBS
Contractors:
- MARCON EXCAVATING AND CONSTRUCTION INC
Permit Reviews
Permit Number - T19CM05885
Permit Status: Final
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/15/2021 | REVISION - - 1ST | 03/23/2021 | COMPLETED |
| 04/12/2021 | REVISION - - 1ST | 04/20/2021 | COMPLETED |
| 08/16/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/16/2019 | COMPLETED |
| 08/16/2019 | RESIDENTIAL - BLDG/WWM | 09/24/2019 | COMPLETED |
| 09/24/2019 | RESIDENTIAL - BLDG/WWM | 10/15/2019 | COMPLETED |
| 10/15/2019 | RESUBMITTAL | 08/28/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05885
Permit Status: Final
Permit Description: SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/16/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM05885
Permit Description: SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2020 | SEPTIC - SYSTEM | DMUNIZ | Approved | Approved. |
| 09/15/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved. |
| 09/18/2020 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
| 09/18/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
| 09/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved |
| 11/25/2020 | FRAMING | DMUNIZ | Approved | Not Ready |
| 11/25/2020 | ROOF NAILING | DMUNIZ | Approved | |
| 11/25/2020 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
| 01/08/2021 | PLUMBING - YARD WTR LINE/TEST | RBOOHER | Approved | plumbing underground approved... |
| 03/05/2021 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE TMPP |
| 03/05/2021 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | |
| 04/08/2021 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
| 04/08/2021 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 04/08/2021 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | |
| 04/08/2021 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
| 04/08/2021 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
| 08/03/2021 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved, okay to backfill |
| 08/03/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved |
| 09/15/2021 | MECHANICAL - FINAL | DMUNIZ | Approved | Approved |
| 09/15/2021 | PLUMBING - FINAL | DMUNIZ | Approved | Approved |
| 09/15/2021 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
| 09/22/2021 | FIRE SPKLR - OH PIPING & HYDRO | wmotto1 | Approved | The overhead pressure test was approved by basaldu. |
| 09/22/2021 | FIRE SPKLR - UG PIPING FLUSH | wmotto1 | Approved | |
| 09/22/2021 | FIRE SPKLR - UG, PIPING, HYDRO | wmotto1 | Approved | |
| 09/27/2021 | BUILDING - FINAL | TGAUSP | Approved | Approved and complete, Fire approved T21FC00060 |