Permit: T19CM05657
Permit Details
Apply Date:
08/07/2019
Applicant:
N/A
Description:
E - COMMERCIAL SOLAR ELECTRIC SYSTEM ADDITION
Contractors:
- WILSON ELECTRIC SERVICES CORP ** APA **
- WILSON ELECTRIC SERVICES CORP
Permit Reviews
Permit Number - T19CM05657
Permit Status: Final
Permit Description: E - COMMERCIAL SOLAR ELECTRIC SYSTEM ADDITION
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2020 | OTHER | 02/24/2021 | COMPLETED |
08/07/2019 | PLANS OK TO SUBMIT - COMM | 08/13/2019 | COMPLETED |
08/13/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/23/2019 | COMPLETED |
09/23/2019 | RESUBMITTAL | 04/19/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05657
Permit Status: Final
Permit Description: E - COMMERCIAL SOLAR ELECTRIC SYSTEM ADDITION
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/07/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM05657
Permit Description: E - COMMERCIAL SOLAR ELECTRIC SYSTEM ADDITION
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/30/2019 | ELECTRIC - UFER | DMUNIZ | Approved | EGC Connection to Steel at Location of Inverters for Canopies D,E,F,G,H,K,L,M ok for concrete encasement. Canopies I,J Not Ready. |
12/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Canopies D,E,F,G,H,K,L,M ok for concrete placement. Canopies I, J Not Ready. |
02/03/2020 | ELECTRIC - UNDERGROUND | WGALLAG1 | Approved | |
03/17/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | |
03/19/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
03/19/2020 | FRAMING | WGALLAGHER | Approved | |
03/24/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE DGC |
03/24/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | Clear TEP DGC |
03/24/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
10/20/2022 | ELECTRIC - INTERMEDIATE | CTREVIL | Approved |