Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM05636
Permit Details
Apply Date:
08/07/2019
Applicant:
Description:
SFR RICH074019 T19-M0041
Permit Reviews
Permit Number - T19CM05636
Permit Status: Expired
Permit Description: SFR RICH074019 T19-M0041
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/07/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/07/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05636
Permit Status: Expired
Permit Description: SFR RICH074019 T19-M0041
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/07/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T19CM05636
Permite Description: SFR RICH074019 T19-M0041
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | COT - RSME - Mechanical Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - RSEL - Outdoor Lighting | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - RSPL - Plumbing Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - RSEL - Electrical Final | N/A | Canceled | Inspection Canceled |
11/07/2022 | COT - RSEL - Service Upgrade | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM05636
Permit Description: SFR RICH074019 T19-M0041
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/21/2019 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/21/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/21/2019 | COT - RSPL - Sewer | Passed | {Activity date: 08/21/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/21/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/21/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/26/2019 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/26/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/26/2019 | COT - RSBU - Preslab | Passed | {Activity date: 08/26/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/26/2019 | COT - RSEL - Electrical Underground | Passed | {Activity date: 08/26/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
08/26/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/26/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
09/17/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/17/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
09/17/2019 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/17/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
10/04/2019 | COT - RSEL - Construction Power | Passed | {Activity date: 10/04/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - (RVI)} | |
10/17/2019 | RSME - Mechanical Progress | Passed | {Activity date: 10/17/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
10/18/2019 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/17/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Provide nail protection where needed for Electrical and plumbing.} | |
10/18/2019 | COT - LCBU - Framing | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/17/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - shim bearing points.} | |
10/18/2019 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/17/2019; Status: Denied; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Provide DWV test on plumbing top out.} | |
10/18/2019 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
10/18/2019 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Clear Southwest Gas.} ; {Activity date: 10/17/2019; Status: Denied; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - No Line Pressure test.} ; {Activity date: 08/26/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
11/07/2019 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 11/07/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by DMERANZ1 - CODE ECO RESEND} ; {Activity date: 10/04/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by DMERANZ1 - CODE ECO} |